SRDP Waves:
Wave 1 | Wave 2 | Wave 3 | Wave 4 | Wave 5 | |
---|---|---|---|---|---|
Development | 2019 | 2020 | 2021 | 2022 | 2023 |
Operation | 2020 | 2021 | 2022 | 2023 | 2024 |
FY21
Project | Description | Target Date | SRDP Deliverables | Pipeline Deliverables | SSA Deliverables | Notes |
---|---|---|---|---|---|---|
SRAO Operations | Calibration of Multiband Datasets | Q2 FY21 | Pipeline Validation | Pipeline Heuristics (Q1 FY21) | ||
Standard Calibration of S-Band observations from the VLA | Q3 FY21 | ? Improved RFI Flagging Algorithms | If RFI Flagging Algorithms | |||
Pilot Imaging Operations for VLA | Q3 FY21 | Validation of VLA Imaging Pipeline | VLA Imaging Pipeline (Q1 FY21) | New workflow to support imaging. Image Ingestion | Pilot to understand resource requirements | |
AUDI Enhancement (Angular Resolution Specification) | Q2 FY21 | Validation of Ang. Resolution Specification | Heuristic Support (Q1 FY21) | Enhancement to AUDI Specification and adaptation to new parameters | ||
Large Program Ingest | Program Support and Product Ingestion | To Be Discussed | ||||
CARTA Integration | SSA Project at this point. | |||||
Image Cutouts | Probably not realistic in FY21 | |||||
SRAO Development | Wave 3: Improved RFI Mitigation for VLA Calibration | Heuristic Definition | Implementation | |||
Wave 3: Imaging Self Cal (ALMA, maybe VLA) | Heuristic Definition | Implementation | ||||
Wave 3: Recalibration | Probably not mostly SSA Effort | |||||
Wave 3: ALMA Group Imaging | Heuristic Definition | Heuristic work, probably not complete | ||||
VLASS Ops | VLASS 2.1 Observing Complete | Q1FY21 | ||||
2.1 QL Imaging Complete | Q2FY21 | |||||
Production of Demonstration set of SE Images | Needs coordination with SCG | |||||
Production of Validation set of SE Images | Q4FY21 | Needs coordination with SCG | ||||
Preparation for VLASS 2.2 Ops | Q4FY21 | |||||
VLASS Development | Production SE Continuum Workflow | Q1FY21 | SE Pipeline Update | Workflow Development | SCG as well | |
SE Polarization Product | Q2FY22 | ARDG | ||||
Catalog Support | Requirements/ Validation | Almost entirely SSA Effort | ||||
TTA Tools | Project Initiation | Q1 FY21 | Available Workforce to begin | |||
Logical Architecture Complete | Q4 FY21 | Requirements and validation | Implementation and Testing | |||
External Goals that Affect SRDP | ||||||
DMS | Authentication and Authorization Design | |||||
CIS | Red Hat 8 | Actual switch is probably FY22 |