This review is conducted to assess the conceptual level requirements and architectural design, as defined within the documents under review.  The review committee is charged by the NRAO Assistant Director of Science Support and Research (SSR) to evaluate the readiness of TTA Tools to proceed from the Conceptual Design stage to detailed design and implementation.  To carry out this charge the review committee should evaluate the project by responding to the following questions:                                                                                                             

  1. Is the defined system (through the system technical description and captured requirements) suitable to support the proposal, review, and allocation processes?
  2. Does the proposed architecture deliver the capabilities as specified in the concept, specification and requirements documents?
  3. Is the project plan (includes the project management plan, estimated budget and schedule, risk analysis) appropriate for this stage of the project? Are the plans and estimates reasonable to achieve the planned scope? 
  4. Does the project team demonstrate overall readiness to proceed to detailed design and implementation phases?

Review Committee

  • Alan Bridger (chair)

  • Craig Heinke
  • Amy Mioduszewski
  • Rachel Osten
  • John Spitzak
  • Joe Swiggum

Design Review Documents

  • 688 TTA Tools Conceptual Design Review Plan (688-TTAT-005-MGMT)
  • 688 TTA Tools Conceptual Design Review Report (688-TTAT-006-MGMT)
  • 688 TTA Tools Project Response to CoDR Report (688-TTAT-0011-MGMT)

Resources


Reference Documents

Project Review Documents

DMS Review Documents

RID Status

Summary of Meeting Topics

Summary of In Review


Error rendering macro 'gadget'

Error rendering gadget [ https://open-jira.nrao.edu/rest/gadgets/1.0/g/com.atlassian.jira.gadgets:stats-gadget/gadgets/stats-gadget.xml ]



Review Schedule

DateActivityResponsible
Jul 6, 2019Appointment of review committee chair.NRAO Director
Feb 7, 2020Committee Appointed

NRAO Director

Committee Chair

Mar 20, 2020Documentation Package Delivered to Committee

Project Director

Project Manager

Mar 21 - Apr 2, 2020


RID Entry and DiscussionCommittee Members

Apr 3 - Apr 9, 2020

RID DispositionProject Team
Apr 15 - Apr 16, 2020Review MeetingCommittee Chair
Apr 16 - Apr 24, 2020Committee Develops ReportCommittee Chair
Apr 27 - May 1, 2020Response to ReportProject Director

Meeting Agenda 

Time

(Eastern)

TopicLead Presenter
Apr 15, 2020
9:00 - 9:30Executive SessionBridger
9:30 - 9:45WelcomeFrail
9:45 - 11:00

System Overview ( Getting issues... )

Kern
11:00 - 11:10Break
11:10 - 12:25

Review Process ( Getting issues... )

Balser
12:25 - 12:55Break
12:55 - 13:45

Architecture ( Getting issues... )

Whitehead
13:45 - 14:10Executive SessionBridger
Apr 16, 2020
9:00 - 9:30Executive SessionBridger
9:30 - 10:30

Workflow ( Getting issues... )

Balser
10:30 - 11:00

Testing ( Getting issues... )

Kern
11:00 - 11:10Break
11:10 - 11:30

Other Issues ( Getting issues... )

Committee
11:30 - 13:00Executive SessionBridger
13:00 - 14:00Initial Findings from the CommitteeBridger