This external review is conducted following establishment of the TTA Tools concept, initial requirement elicitation, and socialization within the user community at several venues. The external review committee is charged by the NRAO director to evaluate the readiness of the TTA Tools project to exit from the project initiation phase and begin the first phase of design and implementation.
Review Schedule
Date | Activity | Responsible |
---|---|---|
Jul 6, 2019 | Appointment of review committee chair. | NRAO Director |
Feb 7, 2020 | Committee Appointed | NRAO Director Committee Chair |
Mar 20, 2020 | Documentation Package Delivered to Committee | Project Director Project Manager |
Mar 21 - Apr 2, 2020 | RID Entry and Discussion | Committee Members |
Apr 3 - Apr 9, 2020 | RID Disposition | Project Team |
Apr 15 - Apr 16, 2020 | Review Meeting | Committee Chair |
Apr 16 - Apr 24, 2020 | Committee Develops Report | Committee Chair |
Apr 27 - May 1, 2020 | Response to Report | Project Director |
Meeting Agenda (TBD)
Time | Topic | Lead Presenter |
---|---|---|
Apr 15, 2020 | ||
Apr 16, 2020 | ||