The DSOC cluster will be offline October 28 and 29 for lustre improvements and to switch the cluster from RHEL6 to RHEL7, this document enumerates the steps we will take beforehand to prepare for it and the steps we will take afterwords to confirm things are working properly and restore access to it.

1 Week Before the Shutdown (October 21)

Morning of the shutdown (October 28)

  • CIS to change external DNS of archive.nrao.edu and archive-new.nrao.edu to point to offline.nrao.edu

Morning After the Shutdown (October 30)

  • Stakeholders (John TobinMark Lacy) test critical functions of the AAT/PPI under RHEL7
  • GO/NO decision:
    • If GO: Stephan Witzto with with CIS to undo the DNS change and MOTD banners
    • If NO-GO: SSA to iterate with stakeholders until result is GO, note that this may mean putting out a bugfix release of AAT/PPI 3.6 and doing the same for VLASS