The objectives of this review are to ensure that:

  • The L1 capabilities projected for delivery to Pilot Operations are ready for verification and validation.
  • That the software system to be tested is under configuration control and is available in the software test environment.
  • That any items not yet ready for test are identified with a plan to advance them to a state of completion and test prior to delivery to Pilot Operations.
  • That a suite of tests sufficient for verification and validation have been defined.

Review Plan

  • This is an internal SRDP Project Office review, the Review Plan is completely described within this Confluence page
  • The Review is scheduled for May 3, 2019

Participants

  • Project Office: Jeff, John, Mark, Bob
  • DMS: Mark Whitehead, Stephan, Kana, Morgan, Andy, David, James

Artifacts Under Review

DateItem or Event and Deadline for AvailabilityResponsible
5/3/2019




RVTM (Requirements Verification Traceability Matrix)SRDP PM

Test Environment Ready (including configuration list) to support the L1 Verification and Validation

DMS
L2 Verification/Validation CompleteDMS/SRDP Heur.

L1 Verification Plan and Test Procedures Complete for the following:

  • OUS Restores
  • VLA Calibration Pipeline
  • Archive Interface
  • Optimized Imaging
DMS
L1 Validation Plan and Test procedures in JiraSRDP Heur.

Operations Process Test Plan

SRDP Ops
5/8/2019Outstanding Issues and incurred Risk DefinedSRDP PM
Report on Outcome of ReviewSRDP PD

Agenda

  1. SRDP Project Director: Opening Remarks
  2. DMS: Test Environment Ready (including configuration list)

  3. SRDP PM: Present Verification and Validation RVTMs; review process to track V&V against the requirements
  4. DMS:  Present L2 verification and validation completion report, based on Jira ticket status
  5. DMS:  Present L1 Verification Plan and Test Procedures, defined within the set of Jira Test Tickets
  6. SRDP Project Scientist: Present L1 Validation Plan and Test procedures defined within the set of Jira Test Tickets
  7. SRDP Operations Mgr.:  Present Operations Process Test Plan defined within the set of Jira Test Tickets: SRDP-336; SRDP-337; SRDP-338, SRDP-340
  8. SRDP Project Director: Preliminary assessment of Test Readiness, itemize any key blockers or major risk to resolve before proceeding

Outcome of Pilot Ops TRR

Report prepared by SRDP Project Director to include:

  • Outcome of review to be one of the following:

    1. Pass: All inputs are satisfactory, no additional risks found, proceed as scheduled.
    2. Risk Identified: One or more risks were identified requiring additional attention.  Risk is not deemed sufficient to affect the schedule.  Risk management plan shall be updated.
    3. Partial Pass: One or more risks are likely to impact schedule of the release.  Re-planning to address risk required.
    4. Fail: Sufficient risk identified to halt the release.  Re-planning or rescoping required.

  • Outcome less than an unconditional "Pass" shall include recommended steps and dates to rectify all discrepencies