Main issue is reporting to TB, but we now also have regular ops reports. Maybe official wind-up of project should be with the Fall 2024 pipeline release (Oct 24)? Need to discuss with AR.
Project RADIAL
Science Ready Data Products
Stephan working on 5 yr SSA plan, will include both new capabilities for SRDP and VLASS and also support of streamlined/automated QA.
~1-10% of early legacy (mostly pre-1986) VLA projects cannot be read into CASA. Bryan and John investigating.
VLASS
Pipeline testing - NCP and cube plane rejection
HPG testing
CIRADA
AOB
Next AI/ML meeting mid- to late-March, focus on VLASS imaging.