This external review is conducted following establishment of the TTA Tools concept, initial requirement elicitation, and socialization within the user community at several venues.   The external review committee is charged by the NRAO director to evaluate the readiness of the TTA Tools project to exit from the project initiation phase and begin the first phase of design and implementation.

Design Review Documents

  • 688 TTA Tools Conceptual Design Review Plan (688-TTAT-005-MGMT)
  • 688 TTA Tools Conceptual Design Review Report (688-TTAT-006-MGMT)
  • 688 TTA Tools Project Response to CoDR Report (688-TTAT-0011-MGMT)

Review Committee

  • Alan Bridger (chair)

  • Craig Heinke
  • Amy Mioduszewski
  • Rachel Osten
  • John Spitzig
  • Joe Swiggum


Reference Documents

Project Review Documents

DMS Review Documents

Status

  • Project documents are available for internal review.
  • Link to a tar file containing all DRAFTs (11 MB).

Review Schedule

DateActivityResponsible
Jul 6, 2019Appointment of review committee chair.NRAO Director
Feb 7, 2020Committee Appointed

NRAO Director

Committee Chair

Mar 20, 2020Documentation Package Delivered to Committee

Project Director

Project Manager

Mar 21 - Apr 2, 2020


RID Entry and DiscussionCommittee Members

Apr 3 - Apr 9, 2020

RID DispositionProject Team
Apr 15 - Apr 16, 2020Review MeetingCommittee Chair
Apr 16 - Apr 24, 2020Committee Develops ReportCommittee Chair
Apr 27 - May 1, 2020Response to ReportProject Director

Meeting Agenda (TBD)

TimeTopicLead Presenter
Apr 15, 2020









Apr 16, 2020