DateItem or Event and Deadline for AvailabilityResponsible
5/3/2019




RVTM (Requirements Verification Traceability Matrix)SRDP PM

Test Environment Ready (including configuration list) to support the L1 Verification and Validation

DMS
L2 Verification/Validation CompleteDMS/SRDP Heur.

L1 Verification Plan and Test Procedures Complete for the following:

  • OUS Restores
  • VLA Calibration Pipeline
  • Archive Interface
  • Optimized Imaging

L1 Verification Plan 5.2.2019

DMS

L1 Validation Plan for Heuristics and Operations Test procedures in Jira

LI Validation Plan 5.2.2019

SRDP Heur.

Operations Process Test Plan

/ SRDP Ops.
5/8/2019Outstanding Issues and incurred Risk DefinedSRDP PM
Report on Outcome of ReviewSRDP PD

...

  • Outcome of review to be one of the following:

    1. Pass: All inputs are satisfactory, no additional risks found, proceed as scheduled.
    2. Risk Identified: One or more risks were identified requiring additional attention.  Risk is not deemed sufficient to affect the schedule.  Risk management plan shall be updated.
    3. Partial Pass: One or more risks are likely to impact schedule of the release.  Re-planning to address risk required.
    4. Fail: Sufficient risk identified to halt the release.  Re-planning or rescoping required.

  • Outcome less than an unconditional "Pass" shall include recommended steps and dates to rectify all discrepenciesdiscrepancies