This review is carried out after the Stakeholder Requirements Review and uses those requirements as the high-level definition of the project scope.  The review committee is charged by the NRAO director to evaluate the readiness of the SRDP project to exit from the project initiation phase and begin the first wave of design and implementation.

Note: This page is reproduced from the original Wiki page as part of the project migration to Confluence.

Review Documents

Review Committee

  • Bruce Berriman (chair)
  • Ian Evans
  • Tracy Clarke
  • Chris Wilson

Documents Under Review

  • Review Documents 

    SRDP Project Documents 

    • pdf Project Charter 
    • pdf Life Cycle Phases and Concepts 
    • pdf Scope Statement
    • pdf NRAO Lexicon and Acronyms
    Project Management 
    • pdf Project Management Plan
      • pdf Stakeholder Register
      • pdf Responsibility Matrix 
      • pdf Schedule
      • pdf Risk Register
      • pdf Cost Management Plan 
    System Engineering 
    • pdf Systems Engineering Management Plan
      • pdf Requirements Committee Terms of Reference
      • pdf Requirements Verification Traceability Matrix
    Stakeholder Requirements and Captured L2 Requirements 
    • pdf System Concept
    • pdf Stakeholder Requirements 
    • pdf L2 Requirements Draft

    Data Management and Software Documents 

    • pdf DMSD Work Management Plan for SRDP
    • pdf SRDP Architecture Description
    • pdf DMSD Software Development Processes

Supplemental Documents

Status

com.atlassian.sal.api.net.ResponseException: Could not parse json from Jira

Review Schedule

Date (2018)ActivityResponsible
February 23Appointment of review committee chair.NRAO Director
Definition of global review schedule and location where review will take place.Committee Chair
March 22Selection of the Review Committee Members

NRAO Director

Committee Chair

March 29Definition of review document packageProject Director
April 16-30Collection and distribution of the review document package to Review Committee Members and briefing of the Committee Members on the current status

Project Manager

Project Director

Review of the document package, preparation, and submittal to the committee chair of queries (RID) on areas requiring further clarification.Committee Members
Response to submitted queries (RID) provided to the Committee members.Project Team
April 30 - May 10Review of unresolved queries (RID) and preparation of Review Meeting agenda.Committee Chair
Preparation of presentation materialProject Team
May 10 - 11Review MeetingCommittee Chair
May 18Completion of Appendix A and B of the Review Report.Project Manager
May 25Completion of the Review Report and distribution to meeting stakeholders.Committee Chair

Meeting Agenda

TimeTopicLead Presenter
May 10, 2018
8:30Executive SessionBerriman
9:00Introduction and WelcomeBeasley
9:15

Context

Kern
10:30Coffee
10:45

Requirements

Kern
12:30Lunch
13:30

Cost Model

Kern
15:15Coffee
15:30

Implementation

Griffith

Kern

16:15

Quality

Kern
16:45Open IssuesAll
17:00Executive SessionBerriman
18:30Dinner at Burton's Grill
May 11, 2018
8:30

Architecture

Hiriart
9:00Topics from the CommitteeBerriman
9:30Executive SessionBerriman
11:30Initial Findings and CloseoutBerriman
12:30Lunch


  • Location: NRAO Headquarters, Edgemont Road