The objectives of this review are to ensure that:

  • The L1 capabilities projected for delivery to Pilot Operations are ready for verification
  • That a test framework is ready to execute
  • That any items not yet ready for test are identified with a plan to advance them to a state of completion and test prior to delivery to Pilot Operations.

Review Plan

  • This is an internal SRDP Project Office review, the Review Plan is completely described within this Confluence page
  • The Review is scheduled for May 3, 2019

Artifacts Under Review

  • L2 verification and validation completion report, based on Jira ticket status
  • L1 Verification Plan, defined as a set of Jira Test Tickets which are rolled up from implementation and test of the L2 tickets
  • L1 Test Procedures that map to L1 Requirements, defined in a set of Jira Test Tickets which include all aspects of integration at the L1 level
  • L1 Validation Plan and Test procedures in Jira
  • Operations Process Test Plan
  • RVTM to track verification and validation against the requirements

DateEvent or Deadline for AvailabilityResponsible

Test Environment Ready to support the L1 Verification and Validation

DMS
5/3/2019L2 Verification/Validation CompleteDMS/SRDP Heur.
5/3/2019

L1 Verification Plan and Test Procedures Complete for the following:

  • OUS Restores
  • VLA Calibration Pipeline
  • Archive Interface
  • Optimized Imaging (Preliminary, based on availability capability)
DMS
5/3/2019L1 Validation Plan and Test procedures in JiraSRDP Heur.
5/3/2019

Operations Process Test Plan

SRDP Ops
5/3/2019RVTM (Requirements Verification Traceability Matrix)SRDP PM
5/10/2019Outstanding Issues and incurred Risk DefinedSRDP PM
5/15/2019Report on Outcome of ReviewSRDP PD

Outcome of Pilot Ops TRR

Report prepared by SRDP Project Director to include:

  • Outcome of review to be one of the following:

    1. Pass: All inputs are satisfactory, no additional risks found, proceed as scheduled.
    2. Risk Identified: One or more risks were identified requiring additional attention.  Risk is not deemed sufficient to affect the schedule.  Risk management plan shall be updated.
    3. Partial Pass: One or more risks are likely to impact schedule of the release.  Re-planning to address risk required.
    4. Fail: Sufficient risk identified to halt the release.  Re-planning or rescoping required.

  • Outcome less than an unconditional "Pass" shall include recommended steps and dates to rectify all discrepencies