You are viewing an old version of this page. View the current version.

Compare with Current View Page History

« Previous Version 16 Next »

Date

Goals

  • Begin imaging with GPUs

Discussion items

ItemWhoNotes
HERA hardwareJames

herastore01d 127013 Racked, disked, needs power and SAS.

herastore02 and four shelves 129289

   * 02a racked and disked.  needs power and SAS

   * 02b racked and empty

   * 02c still in box

   * 02d still in box

aocoss13 130466 racked, booted, needs Lustre

Lustre project quotasjrobnettLustre project quotas are still not quite right. 130900
VLASS RAM swapkroweRestore VLASS memory in nodes at NMT  131614
More HERA nodesjrobnett, krowe

* new herapost-master and make old herapost-master a compute node. Equote: 3000092028924

* new IB card/cable for new herapost-master 132576

* HERA will decide what sort of other nodes they want.

* Buy an IB switch for HERA racks.  $13,300

VLASS SE ImagingJames

Mystery torque failures due to memory,  probably use of vmem (nmpost090)


Key Summary Updated Assignee P Status
Loading...
Refresh

Action items

CAS-13342


  • No labels