Fiscal Year 2022 Planning


Roadmap TargetDescriptionTarget DateGroupPop IDStatusDependenciesNotes

SRAO

Heuristics







Recalibration - VLA

Recalibration support for VLA continuum and VLA spectral line use cases (2 recipes) Heuristics DefinitonQ2


Workspaces;

pipeline recipe


ALMA Standard Images

Serve ALMA standard image products from archive


SSA



AAT


ALMA / VLA Multi-Configuration ImagingDefine heuristics for VLA multi-configuration imagingQ4




SelfCalInitial self-calibration implementation in pipeline (ALMA and VLA) heuristics Defintion

Q3






Weblog Improvement - Defer?






DOIs -? SSA dependency (maybe just for collections)

SSA




VLA User Driven ImagingQ1?




SRAO

Operations





VLA standard calibration

S-band Post VLASS ObservingQ3SRAOQ3


Gain compression fix in pipeline;

Flagging improvements

Compression fix unlikely for Fall 2021 pipeline
VLA standard calibrationL-Band
SRAO

As S-band, but may need TEC maps implemented for polarization projects.Compression fix unlikely for Fall 2021 pipeline
VLA production imaging C→ Q-band

Q2


SRAO

Workspaces
VLA User-driven imaging Pilot

Q4


SRAO

Workspaces/AAT
VLA recalibration

SRAO

Workspaces/AAT

Time critical cal/img

Workflow changes only

Q3

SRAO



Workspaces


Large Project Support

ALFALFA + Others

Other large program ingest?


Enable Large program support

SRAO



AAT

Workspaces?










VLASS








VLASS 2.2 Observing





Q2








VLASS 2.2 QL
Q3




SECI  2.1
Q3




Cube Product DevelopmentPolarization uncertainty in maps characterized and mitigated in pipelineQ1




Pilot Cube Production

Cube imaging (spectral and polarization) requirements defined for Pipeline (an implemented)

Q4




Science Meeting


Q4




Pipeline
Review Meeting
Q2




Cumulative Products 

Should this be a pop goal





Resolved CalibratorsCalibrator model heuristics defined for pipeline implementation





TTA

Tools


Through Phase 12?






Proposal InformationInternalQ1




Review ProcessExternal ValidationQ3




Fiscal Year 2021 Planning


Roadmap TargetDescriptionTarget DateGroupPop IDStatusDependenciesNotes

SRAO

Heuristics






VLA Calibration Pipeline

Improved RFI Mitigation for VLA Calibration
SRAO

COMPLETE


Wave 3 Implementation
VLA Imaging Pipeline

SRAO

COMPLETE



ALMA Imaging PipelineImaging Self Cal (ALMA, maybe VLA)
SRAO

STALLED



Recalibration

Recalibration
SRAO



Minting of DOIs (Requirements)


Q1SRAO

COMPLETE



ALMA Multi-configuration imaging

ALMA Group ImagingQ4SRAO

STALLED


Probably not complete

Catalog Ingestion and Display


Q2SRAO



SRAO

Operations




ALMA Optimized Cube Imaging

Angular Resolution SpecificationQ2SRAO

COMPLETE



VLA Standard Calibration

Calibration of Multiband DatasetsQ2SRAO5.7-13

COMPLETE

Pipeline Heuristics (Q1)
Standard Calibration of S-Band observations from the VLAQ3SRAO5.7-14

FY22



VLA Imaging OperationsPilot Imaging Operations for VLAQ3SRAO5.7-15

IN PROGRESS



CARTA IntegrationPhase 1 CARTA integration with ArchiveQ1SSA6.5-39

IN PROGRESS




Workspaces DeliveryQ2SSA6.5-37

IN PROGRESS



Large Project SupportALFALFAIngest of ALFALFA CollectionQ1SSA6.5-38

STALLED



VLASS








VLASS 2.1 ObservingVLASS 2.1 Observing CompleteQ1VLASS5.7-16

COMPLETE



Quick Look Image ProductionVLASS 2.1 QL Imaging CompleteQ2VLASS5.7-17

COMPLETE



SE Continuum Production




HT Condor for VLASS Continuum ImagesQ1SIS6.5-3

COMPLETE



Demonstrate 100 deg2 of imagingQ1DMS6.5-45

COMPLETE



VLASS SE Imaging Pipeline ReleaseQ2PIPE6.5-30

COMPLETE



Demonstrate Operational SE ImagingQ2DMS6.5-46

IN PROGRESS



Production of Validation set of SE ImagesQ4VLASS5.7-18


Demonstrate at scale ImagingQ4DMS6.5-47


SE Polarization DevelopmentFull-Pol Primary Beam ModellingQ1ARDG6.5-42

COMPLETE




Wide-Field Full Mueller ImagingQ3ARDG6.5-43


VLASS 2.2 ObservingPreparation for VLASS 2.2 OpsQ4VLASS



TTA

Tools


Project InitiationKickoff MeetingQ1TTA

5.7-19


COMPLETE



Logical ImplementationS/W for internal testQ3SSA6.5-40

IN PROGRESS

Follows Integration 1 in TTAT Execution Plan
Implementation through Phase 6

Q4