The DSOC cluster will be offline October 28 and 29 for lustre improvements and to switch the cluster from RHEL6 to RHEL7, this document enumerates the steps we will take beforehand to prepare for it and the steps we will take afterwords to confirm things are working properly and restore access to it. Note that these upgrades won't touch the control systems for the AAT/PPI or VLASS, but they will touch the environment the workflows for both execute on.

1 Week Before the Shutdown (October 21)

Morning of the Shutdown (October 28)

Morning After the Shutdown (October 30)

Stakeholder tests/actions

VLASS actions

VLASS tests