The objectives of this review are to ensure that:
Date | Item or Event and Deadline for Availability | Responsible |
---|---|---|
5/3/2019 | RVTM (Requirements Verification Traceability Matrix) | SRDP PM |
Test Environment Ready (including configuration list) to support the L1 Verification and Validation | DMS | |
L2 Verification/Validation Complete | DMS/SRDP Heur. | |
L1 Verification Plan and Test Procedures Complete for the following:
| DMS | |
L1 Validation Plan for Heuristics and Operations Test procedures in Jira | SRDP Heur. / SRDP Ops. | |
5/8/2019 | Outstanding Issues and incurred Risk Defined | SRDP PM |
Report on Outcome of Review - Delta TRR scheduled for May 17, 2019 | SRDP PD |
DMS: Test Environment Ready (including configuration list)
Report prepared by SRDP Project Director to include:
Outcome of review to be one of the following:
Initial outcome May 3, was a Fail. Significant issues were identified in both the test configuration control, and feature completion. Delta TRR scheduled for May 17 to review progress and assess.
SRDP PM: Review issues since TRR:
Issue Number | Description | References | Impact | Reported by | Date | Owner/Assigned in Jira |
1 | Outstanding requirement to allow selection of pre-release CASA versions within the Archive menu pull down described in SSA-5592 is not in the L1 Doc or model, should this be aded? | SSA-5592 | Revision to Requirements and all downstream artifacts (model, V&V Test, etc), added work to DMS | Jeff Kern | 5/13/2019 | Richard Falardeau |
2 | Spectral cutouts within a spectral window (ALMA Cube Imaging) can only be exported to a single file, unsure if additional exports are overwriting a previously generated file. ALMA exports a single file since cutouts are not supported. | PIPE-345 | Significant inconvenience, workarounds are in discussion | Joe Masters / John Tobin | 5/13/2019 | Kana |
3 | The export of calibration products from the VLA pipeline run is addressed in PIPE-47 is not working as expected | Potential blocker to Pilot Ops | John Tobin | 5/13/2019 | Kana | |
4 | SRDP-251 (ALMA Metadata) missing EBs although the DB was reported as copied from production | SRDP-251 (ALMA), SRDP-253 (VLA) & SSA-5583 | Blocker to Pilot Ops due to partial validation | John Tobin | 5/13/2019 | John Tobin |
5 | Permissions within archive to download to local directories | SRDP-209, SRDP-218, SSA-5268 | Significant inconvenience, no progress since Dec 2018 | John Tobin | 5/13/2019 | John Tobin |
SRDP Project Director: Closing Statement / next steps
Previous date for Mid-Pilot Go/No-Go Decision: July 19, 2019
Revised date for Mid-Pilot Go/No-Go Decision: July 26, 2019
SRDP Project Office: John Tobin, Mark lacy, Bob Treacy
DMS: Morgan Griffith, Mark Whitehead, Stephan Witz, Kana Sugimoto, Joe Masters
Not ready for full testing yet, though some tests can be conducted.
Pipeline is ready, with a follow up SSA item to incorporate pipeline changes in the template (item M1).
SSA is in an all-hands effort to finish the integration work for the product system (SSA-5330), with an estimate of 1-2 days before this is complete. At that point (July 11) attention can be turned to wrapping up other action items listed below.
Changes, particularly to the Request Handler, will require extensive retesting of items previously tested for Pilot. John is confident that he knows what needs to be tested.
Action items in the table below are needed to close the Mid-Pilot TRR and will be reviewed again on July 16.
Issue Number | Description | References | Impact | Reported by | Date | Owner/Assigned in Jira | Status |
---|---|---|---|---|---|---|---|
M1 | Apply PL changes to template | PIPE-389 | No CLI E2E testing until we do this, works with bespoke PPRs | John Tobin | 7/9 | SW/Jim Sheckard | 7/30 - Under validation. PIPE-389 is done, but John has held off on fully calling it validated until he can throw things through the workflow using its features. |
M2 | CLI functional, but changes needed to make it useful for users; need about half a day to do, once product system working | John Tobin | 7/9 | Stephan Witz | 7/11 - memory management issues? 8/6 - SSA-5645 (Critical) looks like the only unresolved ticket in this epic, Ready to Verify | ||
M3 | Adding continuum image (switch) | Generating continuum by default, on/off switch not a blocker | John Tobin | 7/9 | Stephan Witz | 8/6 - Closed | |
M4 | GUI Interface for Archive | Stephan will provide ticket number | Not implemented on test yet, will be addressed after product system integration | John Tobin | 7/9 | Stephan Witz/ Reid Givens | 8/6 - SSA-5392 (design/prototype) Resolved SSA-5173 - Ready to Validate, LSRK question |
M5 | Need time (day or two) to integrate, then will have status | SSA-5330 | Integration/delivery of the product system items is an all-hands effort on the part of the SSA team which blocks work on the other tickets. | Stephan | 7/9 | Stephan Witz | 8/6 - 20 tix. 2 completed/resolved, 0 validation, 7 verifying/ready, 10 scheduled, 1 open |
M6 | SSA-5599, VLA implemented, ALMA in progress, 1) Script to notify Operations manager and DAs when imaging pipeline job is completed and ready for review: status - already exists 2) Script to rerun the imaging pipeline after edits to the PPR and/or extra flagging and/or changes to continuum subtraction: status - not yet done, but could be adapted from existing VLA recaldirs script. 3) Script to ingest image products into the archive and clean up the pipeline directory: status - not yet done (needs product system) | Scripts needed for ALMA, will address when product system items completed. | Mark Lacy | 7/9 | Stephan Witz | 7/29 - Are there critical tasks in this epic, or do they all need to be done? 8/6 - 14 tix, 3 closed/resolved, 4 ready for validation, 2 ready/under verification, 4 scheduled | |
M7 | Run jobs as almapipe in CV, as they run as vlapipe, need to check/configure ACLs | SSA-5689 | Operational efficiency, jobs should run the same way in both environments | Mark Lacy | 7/9 | Stephan Witz |
9:30 MT/ 11:30 ET SOC-280, ER-331
VideoHubIP: 192.33.117.12##6519
AudioHub: 434-817-6286
0) General status - Stephan
1) Review List from last TRR (above)
2) Scripts & script tickets - need to separate mid-Pilot script tickets from others: (SSA-5999, SSA-5621)
3) Any new things?
4) Next steps
Aug 6 Mid-Pilot Delta TRR (this meeting)
Aug 20 Ends validation window
Aug 22 Operations Readiness Review
Aug 27 Operations Go/NoGo
SRDP Project Office: John Tobin, Mark Lacy, Bob Treacy
DMS: Morgan Griffith, Mark Whitehead, Stephan Witz, Kana Sugimoto, Joe Masters
Review Open Issues from July 9