Review Plan
- This is an internal SRDP Project Office review, the Review Plan is completely described within this Confluence page
- The Review is scheduled for June 3, 2019 1:00 PM EDT, 11:00 AM MDT
Participants
- Project Office: Jeff Kern, John Tobin, Mark Lacy, Bob Treacy
- DMS: Morgan Griffith, Andy Hale, (Also invited: David Halstead, James Robnett, Mark Whitehead, Stephan Witz, Kana Sugimoto, Pat Murphy)
Review Items and Events
Date | Item or Event and Deadline for Availability
| Responsible |
---|
6/3/2019
| L1 Verification Results | DMS |
L1 Heuristics Validation Results | SRDP Heuristics |
L1 Ops Validation Results | SRDP Ops |
Production Environment Configuration List | DMS |
Completed RVTM Master | SRDP PM/SE |
6/4/2019 | Outstanding Issues, Action Items, and incurred Risk Defined | SRDP PM/SE |
6/7/2019 | Report on Outcome of Review | SRDP PD |
Pilot ORR Agenda (Preliminary: specific items will be added prior to the review)
SRDP Project Director: Opening Remarks
- DMS: Present L1 Verification Results, defined within the set of Jira Test Tickets
- SRDP Project Scientist: Present L1 Heuristics Validation Results, defined within the set of Jira Test Tickets
- SRDP Operations Manager: Present L1 Operations Validation Results, defined within the set of Jira Test Tickets
- DMS: Present L2 Production Environment Configuration List
- SRDP PM: Present Verification and Validation RVTMs
- SRDP Operations Manager: Status of resources
- ALL: Plan for Late Pilot Deliveries, Test, and Deployment
- ALL: Open Discussion, Any other Issues?
- SRDP Project Director: Opening Remarks
Outcome of Pilot Operations Readiness Review (ORR)
Report prepared by SRDP Project Director to include:
Outcome of review to be one of the following:
- Pass: All inputs are satisfactory, no additional risks found, proceed as scheduled.
- Risk Identified: One or more risks were identified requiring additional attention. Risk is not deemed sufficient to affect the schedule. Risk management plan shall be updated.
- Partial Pass: One or more risks are likely to impact schedule of the release. Re-planning to address risk required.
- Fail: Sufficient risk identified to halt the release. Re-planning or rescoping required.
- Outcome less than an unconditional "Pass" shall include recommended steps and dates to rectify all discrepancies
SRDP Project Director: ORR Report / next steps
Mid-Pilot Operations Readiness Review (ORR) Agenda
Review Plan
- This is an internal SRDP Project Office review, the Review Plan is completely described within this Confluence page
- The Review is scheduled for Sep 4, 2019 Time TBD
- The Review is followed by a Go/NoGo decision on Sep 9, 2019 for release to operations