The objectives of this review are to ensure that:

Review Plan

Participants

Artifacts Under Review

DateItem or Event and Deadline for AvailabilityResponsible
5/3/2019




RVTM (Requirements Verification Traceability Matrix)SRDP PM

Test Environment Ready (including configuration list) to support the L1 Verification and Validation

DMS
L2 Verification/Validation CompleteDMS/SRDP Heur.

L1 Verification Plan and Test Procedures Complete for the following:

  • OUS Restores
  • VLA Calibration Pipeline
  • Archive Interface
  • Optimized Imaging
DMS
L1 Validation Plan and Test procedures in JiraSRDP Heur.

Operations Process Test Plan

SRDP Ops
5/8/2019Outstanding Issues and incurred Risk DefinedSRDP PM
Report on Outcome of ReviewSRDP PD

Agenda

  1. SRDP Project Director: Opening Remarks
  2. DMS: Test Environment Ready (including configuration list)

  3. SRDP PM: Present Verification and Validation RVTMs; review process to track V&V against the requirements
  4. DMS:  Present L2 verification and validation completion report, based on Jira ticket status
  5. DMS:  Present L1 Verification Plan and Test Procedures, defined within the set of Jira Test Tickets.
  6. SRDP Project Scientist: Present L1 Validation Plan and Test procedures defined within the set of Jira Test Tickets
  7. SRDP Operations Mgr.:  Present Operations Process Test Plan defined within the set of Jira Test Tickets.
  8. SRDP Project Director: Preliminary assessment of Test Readiness, itemize any key blockers or major risk to resolve before proceeding

Outcome of Pilot Ops TRR

Report prepared by SRDP Project Director to include: