Goals

  • Begin imaging with GPUs

Discussion items

ItemWhoNotes
HERA hardwareJames

Done: Ticket to rack herastore01d 127013

Ticket to rack herastore02 and shelves 129289

Lustre aocoss13 130466 Peter started installing aocoss13 Jun. 3, 2021

Lustre project quotasjrobnettLustre project quotas are still not quite right. 130900
VLASS RAM swapkroweRestore VLASS memory in nodes at NMT  131614
More HERA nodesjrobnett, krowe

* new herapost-master and make old herapost-master a compute node. Equote: 3000092028924

* new IB card/cable for new herapost-master 132576

* HERA will decide what sort of other nodes they want.

* Buy an IB switch for HERA racks.  $13,300

VLASS SE ImagingJamesMystery torque failures due to memory,  probably use of vmem

Key Summary Updated Assignee P Status
Loading...
Refresh

Action items

CAS-13342