You are viewing an old version of this page. View the current version.

Compare with Current View Page History

« Previous Version 11 Next »

Date

Goals

  • Begin imaging with GPUs

Discussion items

ItemWhoNotes
HERA hardwareJames

Done: Ticket to rack herastore01d 127013

Ticket to rack herastore02 and shelves 129289

Lustre aocoss13 130466 Peter started installing aocoss13 Jun. 3, 2021

Lustre project quotasjrobnettLustre project quotas are still not quite right. 130900
VLASS RAM swapkroweRestore VLASS memory in nodes at NMT  131614
More HERA nodesjrobnett, krowe

* new herapost-master and make old herapost-master a compute node. Equote: 3000092028924

* HERA will decide what sort of other nodes they want.

* Buy an IB switch for HERA racks.  $13,300

Key Summary Updated Assignee P Status
Loading...
Refresh

Action items

CAS-13342


  • No labels