Time: 10:00 ET (8:00 MT)
- Meeting Rooms:
- Edgemont Road: 230
- Socorro: 317
- VideoHubIP: 192.33.117.12##6516
- AudioHub: 434-817-6283
SSA Development Targets
VLASS:
- Production Single Epoch Calibration workflow (Type A&B tiles I think)
- Production Single Epoch Continuum imaging workflow (Parallel, with production source extraction)
- We will be running this on selected fields within a tile so need a method to edit the list of fields.
- Must be parallel (in imaging)
- Design for the future of the VLASS Manager <- architecture project
- VLASS Collections
SRDP:
- (Assume that PI driven cubes are already done)
- Workspace
- CARTA
- A3 (design)
- Alma Image Ingest (standard products)
Schedule
Mid Pilot:
- TRR: 6/28
- ORR: 7/9
- Go/NoGo: 7/12
Wave 1:
- TRR: 11/4/19
- ORR: 11/13/19
- Go/NoGo: 11/18/19
Wave 2:
- Capability Definition: 8/2/19
- L1 Definition 8/30/19
- L2 Definition: 3/13/20
- Implementation: 7/31/20
- V & V: 9/25/20
- ORR: 11/15/20
- Deploy: 12/2/20