The objectives of this review are to ensure that:
- The L1 capabilities projected for delivery to Pilot Operations are ready for verification and validation.
- That the software system to be tested is under configuration control and is available in the software test environment.
- That any items not yet ready for test are identified with a plan to advance them to a state of completion and test prior to delivery to Pilot Operations.
- That a suite of tests sufficient for verification and validation have been defined.
Review Plan
- This is an internal SRDP Project Office review, the Review Plan is completely described within this Confluence page
- The Review is scheduled for May 3, 2019
Participants
- Project Office: Jeff, John, Mark, Bob
- DMS: Mark Whitehead, Stephan, Kana, Morgan, Andy, David, James
Artifacts Under Review
Date | Item or Event and Deadline for Availability | Responsible |
---|---|---|
5/3/2019 | RVTM (Requirements Verification Traceability Matrix) | SRDP PM |
Test Environment Ready (including configuration list) to support the L1 Verification and Validation | DMS | |
L2 Verification/Validation Complete | DMS/SRDP Heur. | |
L1 Verification Plan and Test Procedures Complete for the following:
| DMS | |
L1 Validation Plan for Heuristics and Operations Test procedures in Jira | SRDP Heur. / SRDP Ops. | |
5/8/2019 | Outstanding Issues and incurred Risk Defined | SRDP PM |
Report on Outcome of Review | SRDP PD |
Agenda
- SRDP Project Director: Opening Remarks
DMS: Test Environment Ready (including configuration list)
- SRDP PM: Present Verification and Validation RVTMs; review process to track V&V against the requirements
- DMS: Present L2 verification and validation completion report, based on Jira ticket status
- DMS: Present L1 Verification Plan and Test Procedures, defined within the set of Jira Test Tickets
- SRDP Project Scientist: Present L1 Validation Plan and Test procedures defined within the set of Jira Test Tickets
- SRDP Operations Mgr.: Present Operations Process Test Plan defined within the set of Jira Test Tickets: SRDP-336; SRDP-337; SRDP-338, SRDP-340
- SRDP Project Director: Preliminary assessment of Test Readiness, itemize any key blockers or major risk to resolve before proceeding
Outcome of Pilot Ops TRR
Report prepared by SRDP Project Director to include:
Outcome of review to be one of the following:
- Pass: All inputs are satisfactory, no additional risks found, proceed as scheduled.
- Risk Identified: One or more risks were identified requiring additional attention. Risk is not deemed sufficient to affect the schedule. Risk management plan shall be updated.
- Partial Pass: One or more risks are likely to impact schedule of the release. Re-planning to address risk required.
- Fail: Sufficient risk identified to halt the release. Re-planning or rescoping required.
- Outcome less than an unconditional "Pass" shall include recommended steps and dates to rectify all discrepancies