Date:

Time: 10:30 ET (8:30 MT)

Link to Zoom Meeting

(zoom03 this week)




Agenda

  • News

    • Lustre instability at DSOC
      • start ramping VLASS back up next week if stable.
  • Program Administration
    • DA search status
      • Committee met, 10 candidates identified for zoom interview.
    • Relative priorities of VLASS items: QL cal/imaging, SE imaging automation, etc.
      • AR keen on automation. 
      • Important to keep up with QL for checking observations and QA automation working well (though tuning possible)
      • Need more SE cont. images for "training set", start these in the background, maybe ask DAs to take responsibility/leadership for specific tasks.
      • Cube production will need new version of the pipeline (which will have some rough QA in it to deal with bad planes). Earliest would be this summer.
      • SSG/CIRADA should be asked where we in the sky we should focus cube productionNeeds some thought, but one possibility would be to work on SE automation during the "lull" between B and BnA in April/May if we are not too far behind on QL.
    • Possibility of cross-training DAs between sites.
      • ML discussed with Erica, will have some effort available before the ALMA call (10th Apr), training to be arranged. More discussion needed.
    • DOIs for VLASS Memos (and other NRAO Memos), eventually for data collections too - discuss with library? 
      • ML discussed with Lance, library has no budget for 3rd party DOI assignment, and the URLs are "never going to change"AR will follow-up.
  • Project Management
    • How to add capabilities ("SRDP 2.0") as part of the transition plan to operations.
      • What might we include? 
        • VLA polarization
        • Interactions with TTA tools+proposal database e.g. for cal strategies, spectral lines.
        • Should consult with users as to their needs.
    • VLASS-CIRADA agreement being revised, current agreement expires 31st March, revision will cover extension through Dec 31st 2025.
  • RADIAL update
    • Dillon and Steve talking to Jennifer about projects for RADIAL students.
  • Science Ready Data Products
    •  Amy set up a meeting to discuss allocations of nodes, HTC/Slurm/Torque etc for 3rd March, 11am ET
    • Selfcal is coming..... (starting pipeline testing)
    • VLA spectral line data
  • VLASS
    •  AAS ABQ splinter session being planned.
    • ML+SSG submitted VLASS pitch to Roman call.
    • SE cube demo release next week
    • 2008 VLASS3.1 images cached so far. Latency ~24d.
  • AOB

Overdue Action Items:

Jira
serverDMS JIRA
columnIdsissuekey,summary,duedate,assignee,customfield_10703
columnskey,summary,due,assignee,Original Due Date
maximumIssues20
jqlQueryfilter="SRDP Overdue Action Items"
serverIdeb2e750b-a83a-387e-8345-36eee8a98f01

Upcoming Action Items:

  •  ML to talk to Tony Remijan and Library about DOIs for Memos
  •  AmyK to organize meeting on HTC/Slurm/Torque use on the clusters.
  •  ML to check with John that automated emails for failed WS cals are on the to-do list for WS2.9