Time: 10:00 ET (8:00 MT)

  • Meeting Rooms:
    • Edgemont Road: 230
    • Socorro: 317
  • VideoHubIP: 192.33.117.12##6516
  • AudioHub: 434-817-6283



Agenda

  • News (all)

  • Project Administration (Jeff)
    • VLASS Transition Plan
    • Requirements for SSA Due July 5
      • See below
  • Project Management (Bob)
    • Review Action Items
    • Schedule: (See Below)
  • TTA Tools (Dana)
  • Heuristics Update (John)
    • 5.4.1/5.4.2 comparison, false positive.
    • Export data fix is now in place.
      • Modify template (needs validation)
  • Operations Update (Mark)
    • 5 SRDP VLA calibration datasets delivered, 11 more rerunning/awaiting QA
    • need to keep an eye on Cville Lustre usage (now up to 22TB out of 49TB estimated for pilot). NM usage is 37TB (regular+SRDP calibrations and restores).
  • Implementation Update (Morgan/ Mark)
  • Information Technology (David)
  • AOB

Overdue Action Items:

Jira
serverDMS JIRA
columnskey,summary,due,assignee,original due date
maximumIssues20
jqlQueryfilter="SRDP Overdue Action Items"
serverIdeb2e750b-a83a-387e-8345-36eee8a98f01

Upcoming Action Items:

Jira
serverDMS JIRA
columnskey,summary,due,assignee,original due date
maximumIssues20
jqlQueryfilter = "SRDP Upcoming Action Items"
serverIdeb2e750b-a83a-387e-8345-36eee8a98f01

SSA Development Targets

VLASS:

  • Production Single Epoch Calibration workflow (Type A&B tiles I think)
  • Production Single Epoch Continuum imaging workflow (Parallel, with production source extraction)
    • We will be running this on selected fields within a tile so need a method to edit the list of fields.
    • Must be parallel (in imaging)
  • Design for the future of the VLASS Manager <- architecture project
  • VLASS Collections

SRDP:

  • (Assume that PI driven cubes are already done)
  • Workspace
  • CARTA
  • A3 (design)
  • Alma Image Ingest (standard products)


Schedule

Mid Pilot:

  • TRR: 6/28
  • ORR: 7/9
  • Go/NoGo: 7/12

Wave 1:

  • TRR: 11/4/19
  • ORR: 11/13/19
  • Go/NoGo: 11/18/19

Wave 2:

  • Capability Definition: 8/2/19
  • L1 Definition 8/30/19
  • L2 Definition: 3/13/20
  • Implementation: 7/31/20
  • V & V: 9/25/20
  • ORR: 11/15/20
  • Deploy: 12/2/20