Objective

The objectives of this review are to ensure the Operations Plan is executable, establish a common baseline for operations expectations, and ensure that the resources necessary for success have been identified. 

Review Documents

Review Committee

  • Anthony Remijan (Chair)
  • Claire
Chandler (pending)
  • Chandler 
  • James Robnett 



Documents Under Review

Reference Materials


Updated Document on Sharepoint

RID Status

Jira Charts
borderfalse
showinfortrue
serverDMS JIRA
jqlproject%20%3D%20SRDP%20and%20component%20%3D%20%22SRDP%20Operations%20Plan%20Review%22
statTypestatuses
chartTypepie
width
isAuthenticatedtrue
serverIdeb2e750b-a83a-387e-8345-36eee8a98f01

James Robnett 

Review Schedule

Date (2019)ActivityResponsible
March 4
, 2019
Appoint review committee chair.SRDP Project Director
March 8
, 2019
Appoint review committee members.SRDP Project Director
March 11
, 2019
Review Materials Available

Project Manager

Ops Manager

March 12-19
, 2019
Review of document, submittal of queries or concerns (RID)Committee Members
Response to submitted queries (RID)Project Team
March 20-25
, 2019
Review of unresolved queries (RID) and preparation of Review Meeting agenda

SRDP Project Director

Committee Chair

TBD
March 28Review MeetingCommittee Chair
Apri 5
, 2019
Completion of the Review Report and distribution to meeting stakeholders.

Committee chair

SRDP Project Manager 

Documents Under Review

  • Available March 11 SRDP Operations Plan (530-SRDP-035-OPER) 

Reference Materials

Status

Meeting Agenda

TimeDescriptionResponsible
12:00Executive SessionRemijan
12:15Issues from RIDsLacy
14:15Executive SessionRemijan
14:45CloseoutRemijan

Meeting Materials


View file
nameRID Summary.pdf
height250
View file
nameTopic For Meeting.pdf
height250
View file
nameoperations_review_v1.pptx
height250



Meeting Logistics

Section
Column
width33%

ER-245

NRAO Headquarters

Charlottesville, VA


Column
width34%


Column
width33%

SO-152

Array Operation Center

Socorro, NM

Meeting Agenda

Review Documents