OSD - Observation Specification Disposition
PPR Proposal Process
To determine what time is available for the new proposals, I first have to build an Available Time Model (ATM). The ATM needs to know about pre-commited time from previous approved proposals (e.g., multi-semester, monitoring), sponsored time, maintenance periods, tests, and then also carry-over from the previous semester. I want to be able to import files to specify this information, inspect the imported information, and modify it on the fly as I need. The ATM also depends on the weather and the hardware sometimes (e.g., VLA configuration).
Expand |
---|
title | user storiesDefining the ATM |
---|
|
As a scheduler I would like to define an available time model (ATM) for my facility so I know how much time is available for new Allocation Requests (ARs) to fill. |
|
|
|
|
|
|
| As a scheduler I want the system to determine the ATM based on the precommitted time and weather constraints. | As a VLA scheduler I want to able to make late modifications to the date ranges easily so I don’t have to restart from scratch. | As a scheduler I want to import a list of proposals from past semesters so the time can be filled in the ATM. | As a scheduler I want to define maintenance periods for the facility such that the ATM will not schedule ARs in those blocks of time. | As a scheduler I want the system to calculate time dependent weather coefficients so the prediction of available time is accurate. | As a VLA scheduler I need the ATM to know what configurations are included in the Solicitation so I can be sure to schedule the appropriate ADs. |
|
| As a VLA scheduler I want to able to make late modifications to the date ranges for configurations easily so I don’t have to delete all of my work. | As a VLA scheduler I want to know if the imported proposals are multi semester, tests, or from carry over projects in the UI so I can keep track of the different types of pre-committed time. | As a scheduler I want to define maintenance periods by LST, duration, and date. |
| As a VLA scheduler I want to set the date ranges for each unique configuration so the system can calculate the time dependent weather coefficients. |
|
| As a scheduler I want the modifications I make in date, etc to update the ATM accordingly. | As a GBT scheduler I want to block out time for monitoring projects so I can account for pre committed time that is fixed date accurately. |
|
|
|
|
...
To inspect the ATM, it is most useful to use a pressure plot, which is essentially a histogram of number of the hours requested by the OSDs per time. This tells me how many hours in a certain time bin is being requested or is available. The amount available is many inputs, including weather, frequency, and precommitted time. The amount requested depends on the OSDs of the new proposals. I need to balance the new request against what is available. To do so, I need to really understand the details of both the available time and the requested time. It would also be nice to have a calendar-like view of the ATM, as some of the pre committed time is fixed date.
Expand |
---|
title | user storiesBuilding the ATM |
---|
|
As a scheduler I want the system to build the Pressure Plots ATM so I can understand the available and requested time demands. |
|
|
|
| As a scheduler I want to inspect the ATM so I can check it is correct. | As a scheduler I want to modify the ATM manually at any point so it can be accurate. | As a scheduler I want to be able to interact with the pressure plot visual tools so I can identify ADs:OSDs. |
| As a scheduler I would like to generate a Pressure Plot to represent the ATM so I have a holistic view of the available Time. | As a scheduler I want the pressure plots the visual tools I use to inspect the ATM to update when I change the ATM so they will be correct. | As a scheduler I want an easy way to modify an OSD I have identified in the pressure plot so I don't waste time tracking it down. |
| As a scheduler I want to inspect the ATM in detail so I understand where it may be under or over subscribed. |
| As a scheduler I want a way to identify underutilized LST/GST ranges so I can modify SPs to efficiently fill those ranges. |
| As a scheduler I want a view that is like a calendar so I can review specific days for fixed date observations of pre-committed time. |
| As a scheduler I want a way to identify overfilled LST/GST ranges so I can modify SPs as necessary. |
|
...
Small adjustments in the ATM or and OSD can have big consequences for the available time. As a scheduler, I explore how these changes can make an efficient schedule. As there are a lot of working parts though (many proposals, many inputs to the ATM), I like to return to previous states to assess the impact of a small adjustment. I would like to be able to save a version the schedule so I can return to it later if needed. I would like a detailed version history so I can inspect many different versions if I need to.
Expand |
---|
title | user storiesVersion Control |
---|
|
As a scheduler I would like version control on my work so I can easily access different versions of the schedule I am building. |
|
| As a scheduler, I want to be able to give the versions a useful name so I can keep track of my work versus other schedulers changes. |
| As a scheduler I want to be able to an AD back to the what the AR was so I can start fresh. |
|
Now that I have the ATM, I can start to assess how the new requests will fit into it. I will need to modify the requests but I want to preserve the original request too. I likely will need to do detailed modifications, like to the sources, resources, or requested time, but sometimes I only want to do broad changes, such as total time. Sometimes these changes will have profound impacts on the intent of the request so I want to make sure I can let the PI and the TAC know about these proposed changes. My main intent is to determine preliminary scheduling priorities and to make sure the information needed for the TAC is accurate.
Expand |
---|
title | user storiesModifying OSDs by Hand |
---|
|
As a scheduler I want to each Observation Specification Disposition to have a Scheduling Priority. |
|
|
|
|
|
|
|
| As a scheduler I want to copy the OSs associated within this Solicitation into Observation Specification Dispositions (OSDs) so I can modify the OSDs without modifying the OSs. | As a scheduler I would like to inspect the ADs:OSDs associated with this Solicitation so I can decide if their information is accurate. | As a scheduler I would like to modify ADs:OSDs as needed so I can update their information. | As a scheduler I want to see the SRP’s review of about the proposal. | As a scheduler I want to set a “Manual Construction Required” flag per OSD so the proposer will know they have to regenerate their OSs before observing. | As a scheduler I want an OSD to have one Scheduling Priorities (SP) of either A, B, C, F, and N. | As a scheduler I want to set manually the Preliminary Scheduling Priority (SP) for OSDs. |
|
| As a scheduler I want to know which OSDs were System Generated vs User Generated. | As a scheduler I want to modify the total duration, repeat count, and LST range of an OSD.** | As a scheduler I want to see the Science Comments to PI, Data Management Comments to PI, Technical Comments to the pI PI and all of the equivalent Internal Comments. |
| As a scheduler I want the ADs with external facilities to be handled differently than internal facilities because their approval process is a different. | As a scheduler I want to know which OSDs need to be modified. |
|
|
| As a scheduler I want to update the information in the Science Target List associated with a OSD***. | As a scheduler I want to know the Scientific Merit Metric of the Proposal. |
| As a scheduler I want ADs with external facilities to either be approved or declined instead of having scheduling priorities. | As a scheduler I want to change the SP of an OSD between any defined in the system (e.g N, F, A, B, C). |
|
|
| As a scheduler I want to enter Internal Comments for the TAC on each AD so I can keep notes about my process. |
|
|
| As a scheduler I want to be able to filter on the list of ADs:OSDs so I can easily inspect them. |
|
|
| As a scheduler I want to enter TAC Comments to the PI for each AD so I can prepare for the TAC. |
|
|
| As a scheduler I want to bulk edit the SP of a selected set of OSDs. |
|
|
|
|
|
|
| As a scheduler I want to be able to filter by Proposal ID. |
|
There are some tasks that would be useful if they were automated, as it would take me too long to compile the data by hand. For example, I need to identify source conflicts based on a variety of criteria. I also want OSDs associated with external facilities to be handled differently than OSDs of internal facilities. Finally, I want to use algorithms to help efficiently assign scheduling priorities to OSDs as it may well enough for most cases. That frees up time for me to concentrate on the edge cases and optimization. It is important that I can control which OSDs are having their SPs modified, so I would like a way to "lock" out changes temporarily so neither the system nor a manual edit can be applied until it is unlocked.
Expand |
---|
title | user storiesModiying OSDs with the System |
---|
|
As a scheduler I want to identify Source Conflicts in the OSDs so I can make a note of them for the TAC. | As a scheduler I want ADs/OSDs that request multi semester observations to be clearly identified in the UI so I can understand how they impact future semesters.As a scheduler I want ADs that have external facilities to be automatically marked with N so they won't be accounted for in the scheduling. | As a scheduler I want the system to generate SPs for OSDs because the algorithm may do the majority of the cases sufficiently. | As a scheduler I want to be able to initiate process multiple times so I can iterate on the assigned SPs given a ATM. |
|
| As a scheduler I want OSDs with SPs of N to not be modified by the algorithm because these OSDs are rejected and will not be scheduled. |
|
|
| As a scheduler I want OSDs with SPs that are locked to not be modified by the algorithm so the SPs of those OSDs do not change. |
|
|
| As a scheduler I want OSDs with SPs of F to not be modified by the algorithm because these are fixed dates. |
|
|
| As a VLA scheduler I want the automated algorithm to be the Prioritizer. |
|
|
| As a scheduler I want to be able to modify a system generated SP because I know better. |
|
|
...
Once I am satisfied assigning scheduling priorities and providing comments for the TAC, I need to generate some reports for the TAC. I need both a summary of the ATM and the OSDs for my facility as well as an overview of the proposals/OSDs. I want these in different formats and I will both want a way to interact with the information associated with the Proposals in an efficient way when I'm at the TAC. I will likely do a lot of filtering by different proposal/OSD attributes. I also will want a way to generate a printed view of these summaries/reports because the TAC likes to look at pdfs too.want to export a Preliminary Facility Report based on a specified version of the ATM+OSDs. A Preliminary Facility Report includes the pressure plots for my facility and a csv with the data (TBD). I will take this data and the pressure plots and externally generate a pdf that is the Facility Report. Eventually, I will want to upload materials for the TAC to use during their discussions. For my facility, I want to upload the Facility Report (pdf) and a presentation (pdf). These documents should accessible through the TAC interface and their access is restricted to the TAC and TTA members. I may need to upload a different copy later, so I will want to replace (without versioning) the uploaded files.
For my proposals requesting my facility, I want to generate a Facility Proposal Summary, where the facility is VLA, VLBA, and GBT. This information should be generated into the TAC page so the TAC members can view it for their meeting. I may want to update the data in the Proposal Summary later for example, after the Large Proposal Meeting is finished.
Expand |
---|
|
Expand |
---|
|
As a scheduler I want to create export a Preliminary Facility Report so I can provide a narrative about the scheduling issues of my Facility which includes an LST (orGST) pressure plot. | As a scheduler I want to create a Proposal Summary so there is a list of relevant information for each proposal which provides context for the TAC meeting discussion | As a scheduler I want to specify which version of the ATM+OSDs are exported. | As a scheduler I want the version of the schedule to be included in the Proposal Summary and for it then to not change for the TAC meeting so I can keep editing a new version of the schedule while the TAC is deliberating. |
| As a scheduler I want a way to trigger deployment of an updated Proposal Summary for the TAC to see. I do not think we want to do this. |
|
Proposal Summary
A Proposal Summary is the primary way a TAC interacts with the proposals and the review process. It is likely an interface with specific details (see TAC meeting, the image linked under Facility Documents, summary.
OSR Proposal Process
As a TTA member for the OSR process, one or more of us will collaborate on reviewing a proposal. Typically for proposals in the OSR process, we don't modify the requests to the extent as in the PPR process: we either accept what they have proposed or decline it. It would be good to have the same tools to edit OSDs as the PPR process, but I won't define ATMs and build reports because this is just one proposal. I will have external information to understand the available time and if this proposal can be accommodated. After modifying OSDs, as a TTA member I perform the Science and Feasibility reviews as well as form the recommendations for Proprietary Time, Approved Time, Scheduling Constraints, and Scheduling Priorities. I need to modify these attributes and provide OSC Comments to the PI and Internal Comments for the OSC in case I want to capture any specific comments for the Director's Delegate's review or the PI. Once I have made my recommendations, I want to finalize. The report for the Director's Delegate's review is technically not part of the OSR. In practice there is no real report that is produced.
Expand |
---|
title | Recommended Allocation Dispositions for OSR |
---|
|
As a TTA member I want each OSD to have a scheduling priority. |
|
|
| As a TTA member I want the same tools as the "Modifying OSDs by Hand". | As a TTA member I want to modify OSC Comments to the PI and Internal Comments from the OSC. |
| As a TTA member I the same tools as "Modifying OSDs by the System" |
|
| As a TTA member I want to be able to reset the OSDs to match the OSs. |
|
|