Meeting Objectives:

  • Review the Submission use cases, write and estimate stories in the backlog.
  • Review the Review Use cases, write and estimate the stories in the backlog.
  • Conduct retrospective of project so far.
  • Conduct usability review of tool

High Level Agenda:

  • August 30
    • TTA 0.2 Use Case Development
  • August 31
    • Complete backlog maintenance for TTA 0.2
    • Usability Review
    • Retrospective

Detailed Agenda


August 30
StartEndTopic
8:309:00Submission use case description. Slides
9:009:30Submission backlog creation and estimation
9:309:45Break
9:4511:00Vetting and Proposal Review Preparation
11:0012:00Mock Proposal Review Process exampleReviewDoc
12:0012:30Working Lunch
12:302:00Mock Proposal Review Process
2:002:30Architecture Review
2:302:45Break
3:155:00Proposal Backlog Creation and Estimation
6:30
Dinner Burton's Grill
August 31
StartEndTopic
8:309:00Observatory Review Use Case
9:009:45Observatory review backlog creation and estimation
9:4510:00Break
10:0012:00TTA 0.2 Backlog Maintenance
12:001:00Lunch
1:002:45TTA V0.1 Usability Discussion
2:453:00Break
3:005:00Project Retrospective

Backlog Summary

Jira
serverDMS JIRA
columnIdsissuekey,summary,customfield_11200
columnskey,summary,Σ Story Points
maximumIssues20
jqlQuerytype = "Epic" and fixVersion = "TTA 0.2:Submission and Review"