Meeting Objectives:

  • Review the Submission use cases, write and estimate stories in the backlog.
  • Review the Review Use cases, write and estimate the stories in the backlog.
  • Conduct retrospective of project so far.
  • Conduct usability review of tool

High Level Agenda:

  • August 30
    • TTA 0.2 Use Case Development
  • August 31
    • Complete backlog maintenance for TTA 0.2
    • Usability Review
    • Retrospective

Detailed Agenda


August 30
StartEndTopic
8:309:00Submission use case description.
9:009:45Submission backlog creation and estimation
9:4510:00Break
10:0011:00Review Preparation
11:0012:00Mock Review Process
12:0012:30Lunch
1:002:00Mock Review Process
2:002:30Architecture Review
2:302:45Break
3:155:00Proposal Backlog Creation and Estimation
August 31
StartEndTopic
8:309:00Observatory Review Use Case
9:009:45Observatory review backlog creation and estimation
9:4510:00Break
10:0012:00TTA 0.2 Backlog Maintenance
12:001:00Lunch
1:002:45TTA V0.1 Usability Review
2:453:00Break
3:005:00Project Retrospective