  • Talk with SSA and VLASS about how we actually use these remote clusters.
    • Staging, flocking, etc
  • Done: Find a spot at DSOC for test system.  253T.
  • Get account number and routing number.
  • Buy test system

Timeline

  • Buy test system as soon as practical (assuming the project is still a go)
    • Does Jeff Kern know if this is a go or not
    • Talk to Matthew about where to put this stuff
      • May 3, 2022 krowe: talked to Matthew and Peter.  RADIAL has space 253T reserved.
  • Buy production system by July
  • Receive production system by Aug
  • Install production system by Dec
  • Running in Jan. 2023

...