- Drop ship everything to the site and assemble on site. This will require an NRAO person on site to assemble with a pre-built OS disk for the head node. I think this is too much work to do on site.
- Install DIMMs in nodes
- Install NVMe drives in nodes
- Rack everything
- Cable everything
- Configure switch
- Install/Configure OS
- Ship everything here and assemble then ship a rack-on-pallet.
- Mix the two. Ship minimal stuff here (head node, switch, couple of compute nodes, etc) and configure and drop ship most of the nodes to the site.
- Re-ship head node, switch, compute nodes to site
- Re-ship memory and drives to site
- A person from the remote site could travel to NM or CV to see the test system and get instruction.
...