Info |
---|
This page is a living version of the capability development road map (For the Operations Roadmap go here). On the left side for each wave are the things that we have officially said we were going to do in the concept document. In the middle are user facing things things that we want to make sure we do. It is intended in the sense of "don't forget we wanted to do X". On the right hand side are internal project that we want to do, or technical debt we have incurred that we need to pay off. |
Table of Contents | ||
---|---|---|
|
Programatic Milestones | User Facing Capabilities | Internal / Technical Debt |
---|---|---|
Wave 1: 2019 Development / 2020 Deployment | ||
|
|
|
Wave 2: 2020 Development / 2021 Deployment | ||
|
|
|
Wave 3: 2021 Development / 2022 Deployment | ||
|
| |
Wave 4: 2022 Development / 2023 Deployment | ||
|
| |
Wave 5: 2023 Development / 2024 Deployment | ||
|
|