Versions Compared

Key

  • This line was added.
  • This line was removed.
  • Formatting was changed.

Fiscal Year 2022 Planning
Anchor
SRDPPOPFY22
SRDPPOPFY22


Roadmap TargetDescriptionTarget DateGroupPop IDStatusDependenciesNotes

SRAO

Heuristics







Recalibration - VLA

Recalibration support for VLA continuum and VLA spectral line use cases (2 recipes) Heuristics DefinitonQ2


Workspaces;

pipeline recipe


ALMA Standard Images

Serve ALMA standard image products from archive

Q2

SSA

6.5-35


AAT


ALMA / VLA Multi-Configuration ImagingDefine heuristics for VLA multi-configuration imagingQ4




SelfCalInitial self-calibration implementation in pipeline (ALMA and VLA) heuristics Defintion

Q3






Weblog Improvement - Defer?






DOIs -? SSA dependency (maybe just for collections)

SSA



VUDI PilotVLA User Driven Imaging PilotQ1Q4SSA6.5-37


SRAO

Operations





VLA standard calibration

S-band Post VLASS ObservingQ3SRAO5.7-14


Gain compression fix in pipeline;

Flagging improvements

Compression fix unlikely for Fall 2021 pipeline
VLA standard calibrationL-Band
SRAO

As S-band, but may need TEC maps implemented for polarization projects.Compression fix unlikely for Fall 2021 pipeline
VLA production imaging C→ Q-band

Q2


SRAO5.7-13
Workspaces
VLA User-driven imaging Pilot

Q4


SRAO5.7-16
Workspaces/AAT
VLA recalibration

SRAO

Workspaces/AAT

Time critical cal/img

Workflow changes only

Q3

SRAO

5.7-15


Workspaces


Large Project Support

ALFALFA + Others

Other large program ingest?


Enable Large program support

SRAO



AAT

Workspaces?










VLASS








VLASS 2.2 Observing





Q2



VLASS5.7-17




VLASS 2.2 QL
Q3VLASS5.7-18


SECI  2.1
Q3VLASS5.7-19


Cube Product DevelopmentPolarization uncertainty in maps characterized and mitigated in pipelineQ1SRAO5.7-20

Status
colourGreen
titleComplete



Pilot Cube Production

Cube imaging (spectral and polarization) requirements defined for Pipeline (an implemented)

Q4 Q3
SRAO5.7-21
Pipeline

Science Meeting


Q4

SRAO5.7-23




Review Meeting
Q2SRAO5.7-22

Moved to Q3

Cumulative Products 

Should this be a pop goal





Resolved CalibratorsCalibrator model heuristics defined for pipeline implementation





TTA

Tools


Through Phase 12?






Proposal InformationInternalQ1TTA5.7-24

Status
colourYellow
titleDelayed



Review ProcessExternal ValidationQ3TTA5.7.25


Fiscal Year 2021 Planning
Anchor
SRDPPOPFY21
SRDPPOPFY21


Roadmap TargetDescriptionTarget DateGroupPop IDStatusDependenciesNotes

SRAO

Heuristics






VLA Calibration Pipeline

Improved RFI Mitigation for VLA Calibration
SRAO

Status
colourGreen
titleComplete


Wave 3 Implementation
VLA Imaging Pipeline

SRAO

Status
colourGreen
titleComplete



ALMA Imaging PipelineImaging Self Cal (ALMA, maybe VLA)
SRAO

Status
colourRed
titleFY22



Recalibration

Recalibration
SRAO



Minting of DOIs (Requirements)


Q1SRAO

Status
colourGreen
titleComplete



ALMA Multi-configuration imaging

ALMA Group ImagingQ4SRAO

Status
colourRed
titleFY22


Probably not complete

Catalog Ingestion and Display


Q2SRAO



SRAO

Operations




ALMA Optimized Cube Imaging

Angular Resolution SpecificationQ2SRAO

Status
colourGreen
titleComplete



VLA Standard Calibration

Calibration of Multiband DatasetsQ2SRAO5.7-13

Status
colourGreen
titleComplete

Pipeline Heuristics (Q1)
Standard Calibration of S-Band observations from the VLAQ3SRAO5.7-14

Status
colourRed
titleFY22



VLA Imaging OperationsPilot Imaging Operations for VLAQ3SRAO5.7-15

Status
colourRed
titleFY22



CARTA IntegrationPhase 1 CARTA integration with ArchiveQ1SSA6.5-39

Status
colourGreen
titleComplete




Workspaces DeliveryQ2SSA6.5-37

Status
colourRed
titleFY22



Large Project SupportALFALFAIngest of ALFALFA CollectionQ1SSA6.5-38

Status
colourYellow
titleStalled



VLASS








VLASS 2.1 ObservingVLASS 2.1 Observing CompleteQ1VLASS5.7-16

Status
colourGreen
titleComplete



Quick Look Image ProductionVLASS 2.1 QL Imaging CompleteQ2VLASS5.7-17

Status
colourGreen
titleComplete



SE Continuum Production




HT Condor for VLASS Continuum ImagesQ1SIS6.5-3

Status
colourGreen
titleComplete



Demonstrate 100 deg2 of imagingQ1DMS6.5-45

Status
colourGreen
titleComplete



VLASS SE Imaging Pipeline ReleaseQ2PIPE6.5-30

Status
colourGreen
titleComplete



Demonstrate Operational SE ImagingQ2DMS6.5-46

Status
colourGreen
titleComplete



Production of Validation set of SE ImagesQ4VLASS5.7-18

Status
colourRed
titleFY22



Demonstrate at scale ImagingQ4DMS6.5-47

Status
colourRed
titleFY22



SE Polarization DevelopmentFull-Pol Primary Beam ModellingQ1ARDG6.5-42

Status
colourGreen
titleComplete




Wide-Field Full Mueller ImagingQ3ARDG6.5-43

Status
colourRed
titleFY22



VLASS 2.2 ObservingPreparation for VLASS 2.2 OpsQ4VLASS

Status
colourGreen
titleComplete



TTA

Tools


Project InitiationKickoff MeetingQ1TTA

5.7-19


Status
colourGreen
titleComplete



Logical ImplementationS/W for internal testQ3SSA6.5-40

Status
colourBlue
titleIn Progress

Follows Integration 1 in TTAT Execution Plan
Implementation through Phase 6

Q4