- This is a summary of the phased implementation planning for the new TTA Tools Suite taken from the TTAT Execution Plan.TTA Implementation
Version 0.1:
Jira | ||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|
|
Logical Design Initiation
Objectives:
- Design logical architecture to support solicitation and proposal creation.
1) Review Requirements and walk through Project Docs
Jan. 4, 2021
Feb. 19, 2021
Phase 1: Logical Design of Solicitation and Proposal Submission
Objectives:
- Design and prototype logical architecture to support solicitation and proposal creation.
1) The system shall support definition of multiple concurrent solicitations.
Feb. 22, 2021
April 14, 2021
- Interaction with the A3 component is not required, proxy user identification is sufficient.
- Capabilities and Allocation Requests are stubs consisting of just the facilities and the time requested.
- Scientific Justification need not be populated with actual PDF files.
4) The ability to validate the software through creation and submission of test proposals and
the subsequent removal of proposals when the solicitation is opened shall be demonstrated.
Phase 2: Logical Design of Observatory Site Review and Allocation Disposition Creation
Objectives:
- Design and prototype logical architecture to support a review and time allocation process.
1) Review processes shall be able to be configured on a per solicitation basis.
Review process will be observatory site review.Mar. 9, 2021
April 27, 2021
2) The results of the review shall be entered and persisted, and an allocation disposition created.
- Results shall be entered via a GUI interface. The primary goal is to demonstrate the architectural connections between the UX and application layers.
Phase 3: Logical Design of Allocation Approval, Project Creation, and Process Closeout
Objectives:
- Design and prototype the logical architecture to support the allocation approval, creation of observing projects,
and the closeout of the proposal process.
Mar 17, 2021
May 11, 2021
6) Creation of observing projects for proposals with positive disposition.
- Note that this is a stub project. The intent is to demonstrate that the path to the telescope systems exist and do a minimal population of the project.
Integration: Integration of Phases 1 - 3
Objectives:
- Internal Software Delivery
Technical Debt
Objectives:
- Design and prototype the logical architecture to support the allocation approval, creation of observing projects,
and the closeout of the proposal process.
May 19, 2021
Aug. 4, 2021
Phase 4: Solicitation Definition
Objectives:
- Production level specification of multiple concurrent solicitations.
June 10, 2021
Aug. 24, 2021
Phase 5: High Level Proposal Entry
Objectives:
- Population of the Proposal Information, Author, and Technical Justification portions of proposals.
June 21, 2021
Aug 20, 2021
Phase 6a: Panel-Based Review - Science and Feasibility Reviews
Objectives:
- Implement the Individual Science and Feasibility review processes.
Jun 29,2021
Sep. 8, 2021
Phase 6b: Panel-Based Review - Consensus Meeting
Objectives:
- Implement support for the NRAO Consensus Review.
1) User roles may be by assertion (e.g. users may define themselves to be chair of the science review panel)
July 8, 2021
Sep. 20, 2021