All tickets pertaining to VLASS SE operations should have the VLASS-SE-OPS label.  Add VLASS-SE-DISCUSS label if it should be brought up in this meeting


News

Open Issues

  • Anticipated date for a mosaic vs awp decision for pipelineVLASS has decided to proceed with mosaic as the initial gridder.
  • We need a testing schedule/plan for the transition from development through testing to operations
    • Decision on whether to produce a Mosaic implementation implementation DONE
    • Pipeline available for testing (Done for AWP implementation)
    • SSA PIMS workflow validated (in validation)
    • SSA SE Imaging workflow ready for testing
    • Pipeline validated
    • Pipeline released 
    • SSA SE Imaging workflow validated
    • Begin operations (shooting for June 1st)
    • Migrate above to htcondor (before or after beginning operations ?)

...

  • Jeff will check with Mark on Mosaic decision.  Currently SRDP decision is the pacing issue for pipeline development/release.

Agenda

  • Pipeline
  • Question about parameters for secondary tclean calls, first one is for DA's if things go awry.  The second could have different parameters but is also a DA issue.
  • SSA 
    • PIMS testing status
    SCG
    30 HTcondor nodes now available
    • HTCondor testing 
  • SCG
    • CASA6 bug resolved
    • Beginning to investigate GPU gridder with ARDG

Action items

Ticket Discussions

...