Versions Compared

Key

  • This line was added.
  • This line was removed.
  • Formatting was changed.


Meeting Date

Information that is gathered and tabulated in this page will be reviewed in the weekly DMS/SRDP Meeting:

October 7, 2020 1PM EDT  / 11AM MDT

Objectives of this Review/Retrospective

  • To review processes used in preparation for and during the RH7 (and associated software) upgrade to the VLASS dev/test/prod environments.
  • To improve processes as we prepare for future similar work.
  • To encourage everyone on the team to engage in process improvement
  • To review  what went well and what did not
  • To identify processes and practices that should either change or be discontinued
  • To establish concrete steps to address each item reviewed

Scope of this Review/Retrospective

  • Overall upgrade process
  • Communication
  • Post-upgrade bug identification
  • Ongoing development during upgrade.
  • Processes used for infrastructure deployment and maintenance in dev, test, and production

Roses and Thorns Retrospective Approach

    • Roses:              What is working?
    • Thorns:            What is not working?
    • Buds:               What opportunities can we explore?
    • Fertilizer:         Improvements on existing processes, support for new idea

  • The list has been structured using a "Roses and Thorns" approach
  • The document above is on SharePoint, ready for comments and edits.
  • Everyone on the team is encouraged to make edits directly to the document linked above, please forward this request to your team members and leads
  • The edited document will be discussed and reviewed in the weekly DMS/SRDP meeting on July 1, 2020

Outcome

There is no pass/fail criteria.  An action plan will be incorporated into the document following the meeting and the Project Manager will track and follow up action items.


IDRosesThornsBudsFertilizer
MG-1What went well?What could have gone better?What opportunities can we explore?Improvements on existing processes, support for new ideas.