- Data staging for SE imaging may not be as simple as a 'restore from acrhive' step. VLASS team has investigated and defined the process. Tracked as SCG-107 below
Decisions
- Continuum products needed for Cube imaging will be stored in archive as ancillary products
- No meeting on 8/18, next meeting on 8/25
Agenda
- Pipeline
- <nothing>
- SSA
Is the proposed directory structure (/lustre/aoc/cluster/pipeline/vlass_auto/cache/pims/EB/CAL/DEC/RA) acceptable to everyone
What people want to see as directory components for EBs, calibrations, RA and dec for the phase center. Less essential since it will be mostly managed by the tool
what syntax do people want to use on the CLI to input this information.
- SCG
- Have initial list of 7 data sets
- Will being processing this week.
Action items
Jira | ||||||||||
---|---|---|---|---|---|---|---|---|---|---|
|