Fiscal Year 2021 Planning
Anchor | ||||
---|---|---|---|---|
|
Roadmap Target | Description | Target Date | Group | Pop ID | Dependencies | Notes | |
---|---|---|---|---|---|---|---|
SRAO Heuristics | VLA Calibration Pipeline | Improved RFI Mitigation for VLA Calibration | SRAO | Wave 3 Implementation | |||
VLA Imaging Pipeline | SRAO | ||||||
ALMA Imaging Pipeline | Imaging Self Cal (ALMA, maybe VLA) | SRAO | |||||
Recalibration | Recalibration | SRAO | |||||
Minting of DOIs (Requirements) | SRAO | ||||||
ALMA Multi-configuration imaging | ALMA Group Imaging | SRAO | Probably not complete | ||||
Catalog Ingestion and Display | SRAO | ||||||
SRAO Operations | ALMA Optimized Cube Imaging | Angular Resolution Specification | Q2 | SRAO | 5.2.2-15 | ||
VLA Standard Calibration | Calibration of Multiband Datasets | Q2 | SRAO | 5.2.2-13 | Pipeline Heuristics (Q1) | ||
Standard Calibration of S-Band observations from the VLA | Q3 | SRAO | 5.2.2-14 | ||||
VLA Imaging Operations | Pilot Imaging Operations for VLA | Q3 | SRAO | ||||
CARTA Integration | Phase 1 CARTA integration with Archive | Q1 | SSA | 6.5.39 | |||
Large Project Support | ALFALFA | Ingest of ALFALFA Collection | Q1 | SSA | 6.5.38 | ||
VLASS | VLASS 2.1 Observing | VLASS 2.1 Observing Complete | Q1 | VLASS | 5.2.2-16 | ||
Quick Look Image Production | VLASS 2.1 QL Imaging Complete | Q2 | VLASS | 5.2.2-17 | |||
SE Continuum Production | HT Condor for VLASS Continuum Images | Q1 | SIS | 5.6.3 | |||
Demonstrate 100 deg2 of imaging | Q1 | DMS | 5.6.45 | ||||
VLASS SE Imaging Pipeline Release | Q2 | PIPE | 6.5.30 | ||||
Demonstrate Operational SE Imaging | Q2 | DMS | 6.5.46 | ||||
Production of Validation set of SE Images | Q4 | VLASS | 5.2.2-18 | ||||
Demonstrate at scale Imaging | Q4 | DMS | 6.5.47 | ||||
SE Polarization Development | |||||||
VLASS 2.2 Observing | Preparation for VLASS 2.2 Ops | Q4 | VLASS | ||||
TTA Toos | Project Initiation | Kickoff Meeting | Q1 | TTA | 5.2.3-19 | ||
Logical Implementation | Logical Architecture Complete | Q3 | SSA | 6.5.40 | |||
Implementation through Phase 6 | Q4 |