To accommodate extended WfH requirements due to Covid and a likely segue toward more telecommuting we need to investigate and if possible improve NRAO/NM's broadband access at the home.   

Federal Broadband specification is 25mbit/s down, 3mbit/s up.    Typical DSL from CenturyLink is 15mbit/s down, .5mbit/s up http://www.dslreports.com/speedtest.   Limited upload speed is detrimental to certain interactive services, particularly video conference.

Immediate: (1 week): Put together working team,  flesh out plan

  • Define problem(s) we want to solve,  e.g. do we want to back Socorro efforts to obtain broadband access or simply focus on ensuring minimum requirements for our staff
  • Purely internal focused on short and medium term, may overlap with broader cooperative group working with NMT, Socorro, et al
  • Establish working group (smallish 5 or so at most)
    • Should have both geographic (e.g. Magdalena) and functional representatives (DMS, Electronics, VLA site etc) 

...

Medium term: (1 to 2 months): Ensure Self contained effort to ensure NRAO and staff home networks are working effecientlyefficiently

  • Consider assisting staff with home network issues (e.g. purchase ADSL test meter, have staff test from external NID 
    • Possible electronics staff might be able to help ?
    • Should not require physical contact, test point is external
  • Target fixing 

Long term (1 to 24 months): Develop plan to work with local entities to expand (establish really) Socorro broadband access.