Versions Compared

Key

  • This line was added.
  • This line was removed.
  • Formatting was changed.

This external review is conducted following establishment of the TTA Tools concept, initial requirement elicitation, and socialization within the user community at several venues.   The external review committee is charged by the NRAO director to evaluate the readiness of the TTA Tools project to exit from the project initiation phase and begin the first phase of design and implementation.

Design Review Documents

  • 688 TTA Tools Conceptual Design Review Plan (688-TTAT-005-MGMT)
  • 688 TTA Tools Conceptual Design Review Report (688-TTAT-006-MGMT)
  • 688 TTA Tools Project Response to CoDR Report (688-TTAT-0011-MGMT)

Review Committee

  • Alan Bridger (chair)


Reference Documents

  • SRDP Program Plan (530-SRDP-044-MGMT) (in Draft)

  • TTATools Project Charter (Approved) (688-TTAT-001-MGMT)

  • TTA Tools Concept Document (688-TTAT-002-MGMT) (Requirements Capture) 
  • SRDP Lexicon and Acronyms (688-TTAT-028-MGMT)

Project Review Documents

  • Project Management and Systems Engineering Plan (688-TTAT-003-MGMT)

  • System Description Document (688-TTAT-007-MGMT)
  • TTA Tools Execution Plan (688-TTAT-0010-MGMT)
    1. Description of scheduled implementation phases
    2. Includes resource allocations in FTE estimates
    3. Scope Management and Work Package Descriptions (WBS/Dict equivalency)

  • Risk Register (530-SRDP-006-MGMT)
  • Quality Assurance Plan (688-TTAT-0012-MGMT)

DMS Review Documents

  • Data Management and Software (DMS): Work Management Plan for TTA ToolsSRDP
  • Data Management and Software (DMS): Software Development Processes
  • TTA Conceptual Design (Architecture)
  • Prototyping Plan
  • L0 Requirements Document (688-TTAT-0014-MGMT) (Generated from Cameo)
  • L1 Requirements Document (688-TTAT-0015-MGMT) (Generated from Cameo)Prototyping Plan (TBD)


Status

Review Schedule

DateActivityResponsible
Jul 6, 2019Appointment of review committee chair.NRAO Director
Feb 7, 2020Committee Appointed

NRAO Director

Committee Chair

Mar 20, 2020Documentation Package Delivered to Committee

Project Director

Project Manager

Mar 21 - Apr 2, 2020


RID Entry and DiscussionCommittee Members

Apr 3 - Apr 9, 2020

RID DispositionProject Team
Apr 15 - Apr 16, 2020Review MeetingCommittee Chair
Apr 16 - Apr 24, 2020Committee Develops ReportCommittee Chair
Apr 27 - May 1, 2020Response to ReportProject Director

Meeting Agenda (TBD)

TimeTopicLead Presenter
Apr 15, 2020









Apr 16, 2020