Morning Before the Shutdown (October 27)

  •  Stephan Witz (SSA) to disable CIPL triggers in CAPO for production

Morning of the

...

Shutdown (October 28)

  •  CIS to change external DNS of archive.nrao.edu and archive-new.nrao.edu to point to offline.nrao.edu
  •  SSA to change the casa CAPO properties from the RHEL6 paths to RHEL7 paths

...

  •  Stakeholders (John Tobin, Mark Lacy ) test critical user-facing functions of the AAT/PPI under RHEL7
  •  User-facing things that need to be tested:
    •  Downloads of VLA EBs: SDM-only, SDM, basic MS, CMS
    •  Downloads of VLA calibrations
    •  Downloads of VLASS images
    •  Downloads of VLBA UVFits files
  •  Stakeholders (Mark LacyDrew Medlin) test critical operations-facing functions of the AAT/PPI under RHEL7
  •  Operations-facing things that need to be tested:
    •  EB ingestion
    •  CIPL being triggered
    •  CIPL working
    •  calibration ingestion (QAPass)
  •  GO/NO decision:
    •  If GO: Stephan Witzto with with CIS to undo the DNS change and MOTD banners, re-nable CIPL triggers
    •  If NO-GO: SSA to iterate with stakeholders until result is GO, note that this may mean putting out a bugfix release of AAT/PPI 3.6 and doing the same for VLASS