- PIPE-389 - Template recipe: creation of 'mfs' and 'cont' images
- Status: Ready to validate
- Status: Ready to validate
- SSA-5113 - Epic ticket: Implement ALMA optimized imaging cube capability
- Review Issues under Epic for Blockers and completion target dates
- Status: Actions captured to table below
- SSA-5330 Epic Ticket: Science Products, Ancillary Products and Associations
- Review Issues under Epic for completion target dates
- Status: Actions captured to table below
- (ML) Status of SSA-5599 Epic ticket - workaround scripts for Optimized Imaging workflow corresponding to requirements on Requirements for SSA work-around scripts for pilot, including SSA-5604, SSA-5632, SSA-5605.
- Identify Configuration changes (i.e. versions reflecting changes from these tickets): CASA 5.4.2-7; Archive TBD
- Any Other issues?
- Account permissions etc for DAs and AoD (ML) to run jobs as almapipe. (Status: Captured as M7 in the table below)
- Account permissions etc for DAs and AoD (ML) to run jobs as almapipe. (Status: Captured as M7 in the table below)
- Review and Assign Action Items (Status: Actions captured to table below)
- Outcome:
Not ready for full testing yet, though some tests can be conducted.
Pipeline is ready, with a follow up SSA item to incorporate pipeline changes in the template (item M1).
SSA is in an all-hands effort to finish the integration work for the product system (SSA-5330), with an estimate of 1-2 days before this is complete. At that point (July 11) attention can be turned to wrapping up other action items listed below.
Changes, particularly to the Request Handler, will require extensive retesting of items previously tested for Pilot. John is confident that he knows what needs to be tested.
Action items in the table below are needed to close the Mid-Pilot TRR and will be reviewed again on July 16.
- PIPE-389 - Template recipe: creation of 'mfs' and 'cont' images
Issue Number | Description | References | Impact | Reported by | Date | Owner/Assigned in Jira | Status |
---|---|---|---|---|---|---|---|
M1 | Apply PL changes to template | PIPE-389 | No CLI E2E testing until we do this, works with bespoke PPRs | John Tobin | 7/9 | SW/Jim Sheckard | |
M2 | CLI functional, but changes needed to make it useful for users; need about half a day to do, once product system working | John Tobin | 7/9 | Stephan Witz | |||
M3 | Adding continuum image (switch) | Generating continuum by default, on/off switch not a blocker | John Tobin | 7/9 | Stephan Witz | ||
M4 | GUI Interface for Archive | Stephan will provide ticket number | Not implemented on test yet, will be addressed after product system integration | John Tobin | 7/9 | Stephan Witz/ Reid Givens | |
M5 | Need time (day or two) to integrate, then will have status | SSA-5330 | Integration/delivery of the product system items is an all-hands effort on the part of the SSA team which blocks work on the other tickets. | Stephan | 7/9 | Stephan Witz | |
M6 | SSA-5599, VLA implemented, ALMA in progress, 1) Script to notify Operations manager and DAs when imaging pipeline job is completed and ready for review: status - already exists 2) Script to rerun the imaging pipeline after edits to the PPR and/or extra flagging and/or changes to continuum subtraction: status - not yet done, but could be adapted from existing VLA recaldirs script. 3) Script to ingest image products into the archive and clean up the pipeline directory: status - not yet done (needs product system) | Scripts needed for ALMA, will address when product system items completed. | Mark Lacy | 7/9 | Stephan Witz | ||
M7 | Run jobs as almapipe in CV, as they run as vlapipe, need to check/configure ACLs | SSA-5689 | Operational efficiency, jobs should run the same way in both environments | Mark Lacy | 7/9 | Stephan Witz |
Mid-Pilot delta TRR Agenda - August 6, 2019
...
Key Dates (Tentative)
...
Participants
SRDP Project Office: John Tobin, Mark Lacy, Bob Treacy
DMS: Morgan Griffith, Mark Whitehead, Stephan Witz, Kana Sugimoto, Joe Masters
Review Open Issues from July 9
Agenda
...
...