Comment: added July 9 agenda for Mid Pilot

...

  1. SRDP Project Director: Opening Remarks
  2. SRDP PM: Review Open Actions from TRR
  3. SRDP PM: Review issues since TRR:

    Issue NumberDescriptionReferencesImpactReported byDateOwner/Assigned in Jira
    1Outstanding requirement to allow selection of pre-release CASA versions within the Archive menu pull down described in SSA-5592 is not in the L1 Doc or model, should this be aded?SSA-5592Revision to Requirements and all downstream artifacts (model, V&V Test, etc), added work to DMSJeff Kern5/13/2019Richard Falardeau 
    2Spectral cutouts within a spectral window (ALMA Cube Imaging) can only be exported to a single file, unsure if additional exports are overwriting a previously generated file.  ALMA exports a single file since cutouts are not supported.PIPE-345Significant inconvenience, workarounds are in discussionJoe Masters / John Tobin5/13/2019Kana
    3The export of calibration products from the VLA pipeline run is addressed in PIPE-47 is not working as expectedPotential blocker to Pilot OpsJohn Tobin5/13/2019Kana
    4SRDP-251 (ALMA Metadata) missing EBs although the DB was reported as copied from productionSRDP-251 (ALMA), SRDP-253 (VLA) & SSA-5583Blocker to Pilot Ops due to partial validationJohn Tobin5/13/2019John Tobin
    5Permissions within archive to download to local directoriesSRDP-209, SRDP-218, SSA-5268 Significant inconvenience, no progress since Dec 2018John Tobin5/13/2019John Tobin
  4. Any Other issues?


    1. Pass: All inputs are satisfactory, no additional risks found, proceed as scheduled.
    2. Risk Identified: One or more risks were identified requiring additional attention.  Risk is not deemed sufficient to affect the schedule.  Risk management plan shall be updated.
    3. Partial Pass: One or more risks are likely to impact schedule of the release.  Re-planning to address risk required.
    4. Fail: Sufficient risk identified to halt the release.  Re-planning or rescoping required.

  5. Outcome less than an unconditional "Pass" shall include recommended steps and dates to rectify all discrepancies
  6. SRDP Project Director: Closing Statement / next steps

Mid-Pilot TRR Agenda - July 9, 2019

Participants

SRDP Project Office: John Tobin, Mark lacy, Bob Treacy

DMS: Morgan Griffith, Mark Whitehead, Stephan Witz, Kana Sugimoto, Joe Masters

  1. SRDP PM: Review Open Actions required to deliver Pilot Operations Capability to Validation
    1. PIPE-322 - Implement fluxboot2 fit order heuristics
      • This appears to have converged, John to confirm
    2. PIPE-389 - Template recipe: creation of 'mfs' and 'cont' images
      • SSA has advised on approach, needs target for implementation
    3. SSA-5113 - Epic ticket: Implement ALMA optimized imaging cube capability
      • Review Issues under Epic for Blockers and completion target dates
    4. SSA-5330 Epic Ticket: Science Products, Ancillary Products and Associations
      • Review Issues under Epic for completion target dates
      • Still tagged for SRDP Pilot, No known blockers for Optimized Imaging
    5. Identify Configuration changes (i.e. versions reflecting changes from these tickets)
    6. Any Other issues?
    7. Review and Assign Action Items