The objectives of this review are to ensure that:
- The L1 capabilities projected for delivery to Pilot Operations have been verified and validated.
- That the production software environment is under configuration control.
- That any items not yet ready for delivery are identified with a plan to advance them to a state of completion and test at a date TBD during Pilot Operations.
- That resources needed to support operational processes are ready and committed to achieve operational objectives
Punchlist
Jira server DMS JIRA columns key,summary,type,created,updated,due,assignee,reporter,priority,status,resolution serverId eb2e750b-a83a-387e-8345-36eee8a98f01 key SSA-5649 -
Jira server DMS JIRA columns key,summary,type,created,updated,due,assignee,reporter,priority,status,resolution serverId eb2e750b-a83a-387e-8345-36eee8a98f01 key SSA-5655 -
(specifically, script to rerun the VLA calibration pipeline)Jira server DMS JIRA columns key,summary,type,created,updated,due,assignee,reporter,priority,status,resolution serverId eb2e750b-a83a-387e-8345-36eee8a98f01 key SSA-4535 -
Jira server DMS JIRA columns key,summary,type,created,updated,due,assignee,reporter,priority,status,resolution serverId eb2e750b-a83a-387e-8345-36eee8a98f01 key SSA-5652 -
Jira server DMS JIRA columns key,summary,type,created,updated,due,assignee,reporter,priority,status,resolution serverId eb2e750b-a83a-387e-8345-36eee8a98f01 key SSA-5268 -
Jira server DMS JIRA columns key,summary,type,created,updated,due,assignee,reporter,priority,status,resolution serverId eb2e750b-a83a-387e-8345-36eee8a98f01 key SSA-5659 - (not for SSA, but needed for start of pilot) Helpdesk needs to include "Data Products" Dept.
Review Plan
- This is an internal SRDP Project Office review, the Review Plan is completely described within this Confluence page
- The Review is scheduled for June 3, 2019 1:00 PM EDT, 11:00 AM MDT
Participants
- Project Office: Jeff Kern, John Tobin, Mark Lacy, Bob Treacy
- DMS: Morgan Griffith, Andy Hale, (Also invited: David Halstead, James Robnett, Mark Whitehead, Stephan Witz, Kana Sugimoto, Pat Murphy)
Review Items and Events
Date | Item or Event and Deadline for Availability | Responsible |
---|---|---|
6/3/2019 | L1 Verification Results | DMS |
L1 Heuristics Validation Results | SRDP Heuristics | |
L1 Ops Validation Results | SRDP Ops | |
Production Environment Configuration List | DMS | |
Completed RVTM Master | SRDP PM/SE | |
6/4/2019 | Outstanding Issues, Action Items, and incurred Risk Defined | SRDP PM/SE |
6/7/2019 | Report on Outcome of Review | SRDP PD |
Pilot ORR Agenda (Preliminary: specific items will be added prior to the review)
SRDP Project Director: Opening Remarks
- DMS: Present L1 Verification Results, defined within the set of Jira Test Tickets
- SRDP Project Scientist: Present L1 Heuristics Validation Results, defined within the set of Jira Test Tickets
- SRDP Operations Manager: Present L1 Operations Validation Results, defined within the set of Jira Test Tickets
- DMS: Present L2 Production Environment Configuration List
- SRDP PM: Present Verification and Validation RVTMs
- SRDP Operations Manager: Status of resources
- ALL: Plan for Late Pilot Deliveries, Test, and Deployment
- ALL: Open Discussion, Any other Issues?
- SRDP Project Director: Opening Remarks
Outcome of Pilot Operations Readiness Review (ORR)
Report prepared by SRDP Project Director to include:
Outcome of review to be one of the following:
- Pass: All inputs are satisfactory, no additional risks found, proceed as scheduled.
- Risk Identified: One or more risks were identified requiring additional attention. Risk is not deemed sufficient to affect the schedule. Risk management plan shall be updated.
- Partial Pass: One or more risks are likely to impact schedule of the release. Re-planning to address risk required.
- Fail: Sufficient risk identified to halt the release. Re-planning or rescoping required.
- Outcome less than an unconditional "Pass" shall include recommended steps and dates to rectify all discrepancies
SRDP Project Director: ORR Report / next steps