  • Project Office: Jeff Kern, John Tobin, Mark Lacy, Bob Treacy
  • DMS: Morgan Griffith, Andy Hale,  (Also invited: David Halstead, James Robnett, Mark Whitehead, Stephan Witz, Kana Sugimoto, Pat Murphy)



Date

Item or Event and Deadline for Availability

Responsible

6/3/2019




L1 Verification Results

DMS

L1 Heuristics Validation Results

SRDP Heuristics

L1  Ops Validation Results

SRDP Ops
Production Environment Configuration ListDMS

Completed RVTM Master

SRDP PM/SE
6/4/2019Outstanding Issues, Action Items, and incurred Risk DefinedSRDP PM/SE
6/7/2019Report on Outcome of ReviewSRDP PD

Pilot ORR Agenda (Preliminary: specific items will be added prior to the review)

  1. SRDP Project Director: Opening Remarks

  2. DMS:  Present L1 Verification Results, defined within the set of Jira Test Tickets
  3. SRDP Project Scientist:  Present L1 Heuristics Validation Results, defined within the set of Jira Test Tickets
  4. SRDP Operations Manager:  Present L1 Operations Validation Results, defined within the set of Jira Test Tickets
  5. DMS:  Present L2 Production Environment Configuration List
  6. SRDP PM: Present Verification and Validation RVTMs
  7. SRDP Operations Manager:  Status of resources
  8. ALL:  Plan for Late Pilot Deliveries, Test, and Deployment
  9. ALL:  Open Discussion, Any other Issues?
  10. SRDP Project Director: Opening Remarks

Outcome of Pilot

...

Operations Readiness Review (ORR)

Report prepared by SRDP Project Director to include:

...