  1. SRDP Project Director: Opening Remarks
  2. SRDP PM: Review Open Actions from TRR
    • SRDP-364 - Configuration profiles for Test and Production environments
    • SRDP-363 - Scripts for workspace manager
  3. SRDP PM: Review issues since TRR:

    Issue NumberDescriptionReferencesImpactReported byDateOwner/Assigned in Jira
    1Outstanding requirement to allow selection of pre-release CASA versions within the Archive menu pull down described in SSA-5592 is not in the L1 Doc or model, should this be aded?SSA-5592Revision to Requirements and all downstream artifacts (model, V&V Test, etc), added work to DMSJeff Kern5/13/2019Richard Falardeau 
    2Spectral cutouts within a spectral window (ALMA Cube Imaging) can only be exported to a single file, unsure if additional exports are overwriting a previously generated file.  ALMA exports a single file since cutouts are not supported.PIPE-345Significant inconvenience, workarounds are in discussionJoe Masters / John Tobin5/13/2019Kana
    3The export of calibration products from the VLA pipeline run is addressed in PIPE-47 is not working as expectedPotential blocker to Pilot OpsJohn Tobin5/13/2019Kana
    4SRDP-251 (ALMA Metadata) missing EBs although the DB was reported as copied from productionSRDP-251 (ALMA), SRDP-253 (VLA) & SSA-5583Blocker to Pilot Ops due to partial validationJohn Tobin5/13/2019John Tobin
    5Permissions within archive to download to local directoriesSRDP-209, SRDP-218, SSA-5268 Significant inconvenience, no progress since Dec 2018John Tobin5/13/2019John Tobin
  4. Any Other issues?


    1. Pass: All inputs are satisfactory, no additional risks found, proceed as scheduled.
    2. Risk Identified: One or more risks were identified requiring additional attention.  Risk is not deemed sufficient to affect the schedule.  Risk management plan shall be updated.
    3. Partial Pass: One or more risks are likely to impact schedule of the release.  Re-planning to address risk required.
    4. Fail: Sufficient risk identified to halt the release.  Re-planning or rescoping required.

  5. Outcome less than an unconditional "Pass" shall include recommended steps and dates to rectify all discrepancies
  6. SRDP Project Director: Closing Statement / next steps