DateItem or Event and Deadline for AvailabilityResponsible
5/3/2019




RVTM (Requirements Verification Traceability Matrix)SRDP PM

Test Environment Ready (including configuration list) to support the L1 Verification and Validation

DMS
L2 Verification/Validation CompleteDMS/SRDP Heur.

L1 Verification Plan and Test Procedures Complete for the following:

  • OUS Restores
  • VLA Calibration Pipeline
  • Archive Interface
  • Optimized Imaging

L1 Verification Plan 5.2.2019

DMS

L1 Validation Plan for Heuristics and Operations Test procedures in Jira

LI Validation Plan 5.2.2019

SRDP Heur. / SRDP Ops.
5/8/2019Outstanding Issues and incurred Risk DefinedSRDP PM
Report on Outcome of Review - Delta TRR scheduled for May 17, 2019SRDP PD

Pilot TRR Agenda

  1. SRDP Project Director: Opening Remarks
  2. DMS: Test Environment Ready (including configuration list)

  3. SRDP PM: Present Verification and Validation RVTMs; review process to track V&V against the requirements
  4. DMS:  Present L2 verification and validation completion report, based on Jira ticket status
  5. DMS:  Present L1 Verification Plan and Test Procedures, defined within the set of Jira Test Tickets
  6. SRDP Project Scientist: Present L1 Validation Plan and Test procedures defined within the set of Jira Test Tickets
  7. SRDP Operations Mgr.:  Present Operations Process Test Plan defined within the set of Jira Test Tickets: SRDP-336; SRDP-337; SRDP-338, SRDP-340
  8. SRDP Project Director: Preliminary assessment of Test Readiness, itemize any key blockers or major risk to resolve before proceeding

...

  • Outcome of review to be one of the following:

    1. Pass: All inputs are satisfactory, no additional risks found, proceed as scheduled.
    2. Risk Identified: One or more risks were identified requiring additional attention.  Risk is not deemed sufficient to affect the schedule.  Risk management plan shall be updated.
    3. Partial Pass: One or more risks are likely to impact schedule of the release.  Re-planning to address risk required.
    4. Fail: Sufficient risk identified to halt the release.  Re-planning or rescoping required.

  • Outcome less than an unconditional "Pass" shall include recommended steps and dates to rectify all discrepancies

Pilot (Delta) TRR Agenda - May 17, 2019

  1. SRDP Project Director: Opening Remarks
  2. SRDP PM: Review Open Actions from TRR
    • SRDP-364 - Configuration profiles for Test and Production environments
    • SRDP-363 - Scripts for workspace manager
  3. SRDP PM: Review issues since TRR:

    Issue NumberDescriptionReferencesImpactReported byDateOwner/Assigned in Jira
    1Outstanding requirement to allow selection of pre-release CASA versions within the Archive menu pull down described in SSA-5592 is not in the L1 Doc or model, should this be aded?SSA-5592Revision to Requirements and all downstream artifacts (model, V&V Test, etc), added work to DMSJeff Kern5/13/2019Richard Falardeau 
    2Spectral cutouts within a spectral window (ALMA Cube Imaging) can only be exported to a single file, unsure if additional exports are overwriting a previously generated file.  ALMA exports a single file since cutouts are not supported.PIPE-345Significant inconvenience, workarounds are in discussionJoe Masters / John Tobin5/13/2019Kana
    3The export of calibration products from the VLA pipeline run is addressed in PIPE-47 is not working as expectedPIPE-47Potential blocker to Pilot OpsJohn Tobin5/13/2019Kana
    4SRDP-251 (ALMA Metadata) missing EBs although the DB was reported as copied from productionSRDP-251 (ALMA), SRDP-253 (VLA) & SSA-5583Blocker to Pilot Ops due to partial validationJohn Tobin5/13/2019John Tobin
    5Permissions within archive to download to local directoriesSRDP-209, SRDP-218SSA-5268 Significant inconvenience, no progress since Dec 2018John Tobin5/13/2019John Tobin
  4. Any Other issues?


  5. SRDP Project Director: Closing Statement / next steps