  • L2 verification and validation completion report, based on Jira ticket status
  • L1 Verification Plan, defined as a set of Jira Test Tickets which are rolled up from implementation and test of the L2 tickets.
  • L1 Test Procedures that map to L1 Requirements, defined in Validation Plan and Test procedures defined as a set of Jira Test Tickets which include all aspects of integration at the L1 level
  • L1 Validation Plan and Test procedures in Jira
  • Operations Process Test Plan defined as a set of Jira Test Tickets.Operations Process Test Plan
  • RVTM to track verification and validation against the requirements

5/3/20195/3/20195/3/20195/8/2019
DateEvent or Deadline for AvailabilityResponsible
5/3/2019


Test Environment Ready (including configuration list) to support the L1 Verification and Validation

DMS
L2 Verification/Validation CompleteDMS/SRDP Heur.5/3/2019

L1 Verification Plan and Test Procedures Complete for the following:

  • OUS Restores
  • VLA Calibration Pipeline
  • Archive Interface
  • Optimized Imaging
DMS
L1 Validation Plan and Test procedures in JiraSRDP Heur.

Operations Process Test Plan

SRDP Ops5/3/2019
RVTM (Requirements Verification Traceability Matrix)SRDP PM
5/8/2019Outstanding Issues and incurred Risk DefinedSRDP PM
Report on Outcome of ReviewSRDP PD

...