  • The L1 capabilities projected for delivery to Pilot Operations are ready for verification and validation.
  • That a test framework is ready to executethe software system to be tested is under configuration control and is available in the software test environment.
  • That any items not yet ready for test are identified with a plan to advance them to a state of completion and test prior to delivery to Pilot Operations.
  • That a suite of tests sufficient for verification and validation have been defined.

Review Plan

  • This is an internal SRDP Project Office review, the Review Plan is completely described within this Confluence page
  • The Review is scheduled for May 3, 2019

Participants

  • Project Office: All of us
  • DMS: Stephan, Kana, Morgan, Andy, David

Artifacts Under Review

  • L2 verification and validation completion report, based on Jira ticket status
  • L1 Verification Plan, defined as a set of Jira Test Tickets which are rolled up from implementation and test of the L2 tickets
  • L1 Test Procedures that map to L1 Requirements, defined in a set of Jira Test Tickets which include all aspects of integration at the L1 level
  • L1 Validation Plan and Test procedures in Jira
  • Operations Process Test Plan
  • RVTM to track verification and validation against the requirements

DateEvent or Deadline for AvailabilityResponsible

Test Environment Ready (including configuration list) to support the L1 Verification and Validation

DMS
5/3/2019L2 Verification/Validation CompleteDMS/SRDP Heur.
5/3/2019

L1 Verification Plan and Test Procedures Complete for the following:

  • OUS Restores
  • VLA Calibration Pipeline
  • Archive Interface
  • Optimized Imaging (Preliminary, based on availability capability)
DMS
5/3/2019L1 Validation Plan and Test procedures in JiraSRDP Heur.
5/3/2019

Operations Process Test Plan

SRDP Ops
5/3/2019RVTM (Requirements Verification Traceability Matrix)SRDP PM
5/108/2019Outstanding Issues and incurred Risk DefinedSRDP PM
5/158/2019Report on Outcome of ReviewSRDP PD

...