  • L2 verification and validation completion report, based on Jira ticket status
  • L1 Verification Plan, defined as a set of Jira Test Tickets which are rolled up from implementation and test of the L2 tickets
  • L1 Test Procedures that map to L1 Requirements, defined in a set of Jira Test Tickets which include all aspects of integration at the L1 level
  • L1 Validation Plan and Test procedures in Jira
  • Operations Process Test Plan
  • RVTM to track verification and validation against the requirements

DateEvent or Deadline for AvailabilityResponsible

Test Environment Ready (including configuration list) to support the L1 Verification and Validation

DMS
5/3/2019L2 Verification/Validation CompleteDMS/SRDP Heur.
5/3/2019

L1 Verification Plan and Test Procedures Complete for the following:

  • OUS Restores
  • VLA Calibration Pipeline
  • Archive Interface
  • Optimized Imaging (Preliminary, based on availability capability)
DMS
5/3/2019L1 Validation Plan and Test procedures in JiraSRDP Heur.
5/3/2019

Operations Process Test Plan

SRDP Ops
5/3/2019RVTM (Requirements Verification Traceability Matrix)SRDP PM
5/10/2019Outstanding Issues and incurred Risk DefinedSRDP PM
5/15/2019Report on Outcome of ReviewSRDP PD

Outcome of Pilot Ops TRR

Report prepared by SRDP Project Director to include:

...