The objectives of this review are to ensure the Operations Plan is executable, establish a common baseline for operations expectations, and ensure that the resources necessary for success have been identified.
Review Documents
- Operations Review Plan (530-SRDP-036-MGMT)
- Operations Review Report (530-SRDP-037-MGMT)
Review Committee
- Anthony Remijan (Chair)
- Claire Chandler
- James Robnett
Documents Under Review
- SRDP Operations Plan (530-SRDP-035-OPER)
Reference Materials
- SRDP System Concept (530-SRDP-014-MGMT)
- SRDP Project Management Plan (530-SRDP-003-MGMT)
- SRDP Risk Register (530-SRDP-06-MGMT)
Updated Document on Sharepoint
RID Status
Jira Charts | ||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
|
Review Schedule
Date (2019) | Activity | Responsible |
---|---|---|
March 4 | Appoint review committee chair. | SRDP Project Director |
March 8 | Appoint review committee members. | SRDP Project Director |
March 11 | Review Materials Available | Project Manager Ops Manager |
March 12-19 | Review of document, submittal of queries or concerns (RID) | Committee Members |
Response to submitted queries (RID) | Project Team | |
March 20-25 | Review of unresolved queries (RID) and preparation of Review Meeting agenda | SRDP Project Director Committee Chair |
March 28 | Review Meeting | Committee Chair |
Apri 5 | Completion of the Review Report and distribution to meeting stakeholders. | Committee chair SRDP Project Manager |
Meeting Agenda
Time | Description | Responsible |
---|---|---|
12:00 | Executive Session | Remijan |
12:15 | Issues from RIDs | Lacy |
14:15 | Executive Session | Remijan |
14:45 | Closeout | Remijan |