Attendees
Attendees | Regrets | Notified |
---|---|---|
Agenda
News
- Program Administration
- Project Management
- official closeout date for SRDP project
- Main issue is reporting to TB, but we now also have regular ops reports. Maybe official wind-up of project should be with the Fall 2024 pipeline release (Oct 24)? Need to discuss with AR.
- official closeout date for SRDP project
- Project RADIAL
- Science Ready Data Products
- Stephan working on 5 yr SSA plan, will include both new capabilities for SRDP and VLASS and also support of streamlined/automated QA. Need to make sure this process continues with his successor.
- Timeline for cal+img capability (and implications for ops).
- ~1-10% of early legacy (mostly pre-1986) VLA projects cannot be read into CASA. Bryan and John investigating.
- Intermittent NAASC lustre issues for AUDI & restores.
- Stephan working on 5 yr SSA plan, will include both new capabilities for SRDP and VLASS and also support of streamlined/automated QA. Need to make sure this process continues with his successor.
- VLASS
- Pipeline testing - almost complete?
- HPG testing
- IAU - ML going, put in abstract for sky survey theme in Div J (galaxies & cosmology)
- CIRADA
- Told the CIRADA management committee that we will probably not complete our in-kind contribution (catalogs and convolved coarse cubes) by Dec 31st 2024 when the project wraps up. Likely we can continue to contribute for another 12 months though, which should suffice.
- AOB
- Next AI/ML meeting mid- to late-March, focus on VLASS imaging.